Sanjeev Prashar - Petitioner @HASH Executive Engineer and another

High Court of Himachal Pradesh 24 Jun 2016 Arbitration Case No. 92 of 2015. (2016) 06 SHI CK 0086
Bench: Single Bench
Result Published
Acts Referenced

Judgement Snapshot

Case Number

Arbitration Case No. 92 of 2015.

Hon'ble Bench

Dharam Chand Chaudhary, J.

Advocates

Mr. Vivek Singh Thakur, Advocate, for the Petitioner; Mr. Shrawan Dogra, Advocate General with Mr. Virender Verma, Additional Advocate General, for the Respondents

Final Decision

Dismissed

Acts Referred
  • Arbitration and Conciliation Act, 1996 - Section 11

Judgement Text

Translate:

Mr. Dharam Chand Chaudhary, J.(Oral) - In this petition, a prayer has been made for appointment of Arbitrator.

2. The petitioner is a Government contractor. He was awarded the work namely, (C/o SNP (SH:- RCC Trough on ground & on pedestal for distribution system of distributor D-2 from RD 5210/0 to 2140 Mtr. i/c road crossing at RD, 500, 1300 and 1800 of LBC (CZ). He entered into an agreement after negotiation conducted on 8th June, 2011. He failed to complete the work within the stipulated period, therefore, the respondent-department has levied penalty upon the petitioner @ 10% of the contract amount vide Annexure Ab-10. He preferred an appeal and the Superintending Engineer has reduced the amount of penalty from 10% to 5% and the petitioner was informed accordingly vide order Annexure Ab-11 dated 24.01.2013. It is thereafter final settlement was made in the matter of payment of final bill to the petitioner on 27.07.2013.

3. It has now been claimed that no penalty could have been imposed upon the petitioner-contractor as the delay in execution of the work was not attributed to him but to the respondent-department, as the site was not handed over to him well in time. The petitioner, therefore, has disputed the levy of penalty upon him to the tune of Rs. 6,19,862/- and 1% of the cost of awarded work i.e. Rs. 1,23,972/-. The respondent-department has deducted the amount of penalty so levied and made the final payment.

4. The grouse of the petitioner is that this amount should have not been deducted from his bill. He has, therefore, approached this Court for appointment of Arbitrator under Section 25 of the contract agreement Annexure Ab-1 to resolve the dispute between the parties, he raised in this petition and also the legal notice Annexure Ab-15.

5. In reply, the stand of the respondent-department is that the payment of final bill was made to the petitioner on 27.07.2013 and now after the expiry of 90 days of the settlement of final bill, he is not entitled to invoke the provisions contained in Clause 25 of the contract agreement.

6. The petitioner in rejoinder has further come forward with the version that since the time was extended by the respondent-department on 27.03.2014 vide Annexure Ab-14, therefore, he has served the respondent with legal notice well before the expiry of the period of 90 days.

7. On hearing Mr. Vivek Singh Thakur, learned counsel for the petitioner and Mr. Virender Verma, learned Additional Advocate General on behalf of the respondent-State as well as going through the record of the case, it would not be improper to conclude that the prayer for appointment of Arbitrator has been made by the petitioner beyond the period of 90 days. In terms of Clause 25 of the agreement in case the Contractor fails to demand the appointment of Arbitrator in respect of any claims in writing within 90 days of receiving the information from the Government that the bill is ready for payment, his claim for appointment of Arbitrator will be deemed to have been waived and absolutely barred. Admittedly, the petitioner-Contractor has received the payment of final bill on 27.07.2013. The explanation as set forth, no doubt, is that he was in need of money as he has to make the payment of wages to labour, however, the same is hardly of any help to him because the payment of final bill has been received by him without any protest. Much has been said qua the extension granted vide letter Annexure Ab-14. The perusal of this document reveals that, no doubt, the extension of time was granted in his favour, however, for the past period i.e. w.e.f 4.1.2012 to 25.7.2013 viz., the period before the payment of final bill was made to him. Merely that such sanction has been granted ex-post facto and conveyed to him after the payment of final bill cannot be taken to arrive at a conclusion that he has approached for appointment of Arbitrator within the period of limitation. No doubt, the amount of penalty imposed upon him has been adjusted by the respondent-department while sanctioning the final bill and making the payment to him, however, such dispute cannot be raised beyond the period of 90 days from the date of receipt of final payment. Therefore, there is no merit in the present petition and the same is accordingly dismissed of course with liberty reserved to the petitioner to resort to any other and further remedy, if available to him in accordance with law.

From The Blog
Celina Jaitly Accuses Husband Peter Haag of Domestic Violence, Seeks ₹50 Crore Compensation in Mumbai Court
Nov
26
2025

Court News

Celina Jaitly Accuses Husband Peter Haag of Domestic Violence, Seeks ₹50 Crore Compensation in Mumbai Court
Read More
Supreme Court Flags Disturbing Trend: Criminal Law Misused When Consensual Relationships Break Down
Nov
26
2025

Court News

Supreme Court Flags Disturbing Trend: Criminal Law Misused When Consensual Relationships Break Down
Read More