Aparna Construction and Suppliers Vs State of U.P.

Allahabad High Court 21 Aug 2014 Writ-C No.-65807 of 2013 (2014) 7 ADJ 512 : (2014) 125 RD 324
Bench: Division Bench
Result Published
Acts Referenced

Judgement Snapshot

Case Number

Writ-C No.-65807 of 2013

Hon'ble Bench

Krishna Murari, J; Ashwani Kumar Mishra, J

Advocates

P.N. Tripathi, Advocate for the Appellant

Final Decision

Allowed

Acts Referred

Uttar Pradesh Zamindari Abolition and Land Reforms Act, 1950 — Section 278

Judgement Text

Translate:

Ashwani Kumar Mishra, J.@mdashPetitioner firm is a contractor duly registered with the office of Divisional Forest Officer, Forest Region,

Mirzapur. It claims that pursuant to award of contract, a work order was issued by respondents for construction of 30 houses on 12.11.2010. It is

asserted that the contract work was satisfactorily completed, whereafter a physical verification was also done on 9.9.2011. Subsequently, a team

of officers also conducted physical verification and submitted its report. The Assistant Engineer concerned forwarded the report stating that on

25.10.2012 the verification team found 20 houses to be as per norms. The petitioner thus represented on 2.2.2012 that he has substantially

completed the work and the remaining work is withheld only due to non-release of payment against pending bills and sought release of payment.

The demand for release of payment was also pressed by the petitioner.

2. The petitioner claims that instead of releasing the withheld payment, it was served with an order dated 24.4.2013, cancelling the contract itself

on the ground that the construction since was not completed within a period of six months, as was required in the contract, as such, the contract

was cancelled under Clause 44.1 of the agreement for breach of contract. The petitioner was also informed that losses caused were liable to be

recovered from petitioner by virtue of Clause 45.1 of the Contract. A recovery thereafter under Z.A. Form 68 has been issued on 8.11.2013 for a

sum of Rs. 22,02,454/-, which is under challenge in the present writ petition.

3. We have heard Sri Anil Bhushan, Advocate for the petitioner and learned Standing Counsel for the respondents-State.

4. Sri Anil Bhushan, learned counsel for the petitioner has submitted that:-

(i) Petitioner has not been heard in the matter before issuing the recovery proceedings and thus the impugned action is violative of the principle of

natural justice.

(ii) The liability of petitioner to pay the amount claimed has not been determined in any valid proceedings, and as such, recovery is illegal.

(iii) The amount claimed is in essence a contractual claim, which cannot be recovered as arrears of land revenue.

5. Learned Standing Counsel for the respondents, on the other hand, has submitted that the recovery from the petitioner is of the amount due and

payable to the respondents, and is rightly being realized as arrears of land revenue.

6. We have examined the respective contentions and have perused the records.

7. Petitioner has asserted in Para 12 of the writ petition that the order for cancellation of contract was passed mechanically and without any

opportunity of hearing to the petitioner. The reply of the respondents contained in Paras 8 and 9 of the counter affidavit is wholly vague. No

instance of issuance of any notice to petitioner before determining petitioner''s liability has been brought on record. The letters enclosed along with

the counter affidavit do not go to show that petitioner was given any notice or opportunity before working out the dues, alleged to be payable by

the petitioner. Thus, contention of denial of opportunity to petitioner is borne out from the record.

8. Further contention of Sri Bhushan is that the amount claimed by the respondents, even otherwise, is at best a contractual due, which cannot be

realized from petitioner as arrears of land revenue particularly without any prior adjudication of the liability. A supplementary counter affidavit has

been filed by the respondents to deal with the argument. The respondents have asserted that they are entitled to recover the amount by virtue of

Clause 45.1 of the Contract, which is quoted hereinafter:-

45.1. If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the DFO, Mirzapur shall issue a certificate for

the values of the work done and Materials ordered less liquidated damages, if any less advance payments received up to the date of the issue of

the certificate and less the percentage to apply to the values of the work not completed, as indicated in Contract Date: If the total amount due to

the Employer exceeds any payment due to the Contractor, the difference shall be recovered from the security deposit. If any amount is still left

unrecovered it will be a debt payable to the Employer.

A perusal of the clause relied upon does not show that any amount due to the employer can be recovered as arrears of land revenue.

9. The citation under challenge has been issued on 8.11.2013 by invoking the jurisdiction conferred under Rule 282 of the U.P.Z.A. Rules, 1950.

Rule 282 provides that the proclamation of sale shall be in Z.A. Form 74. Chapter XII of the U.P. Zamindari Abolition and Land Reforms Act,

1950 provides for land revenue and the manner of its realization. Section 278 of U.P.Z.A. & L.R. Act provides that a statement of account

certified by the Tehsildar shall for the purpose of this Chapter, be conclusive evidence of the existence of the arrears of land revenue, of its amount

and of the person who is the defaulter. However, other dues payable can also be recovered as arrears of land revenue, if it is so permitted by law.

Reliance has also been placed upon Section 3 of The U.P. Public Moneys (Recovery of Dues) Act, 1972, which provides for recovery of certain

dues as arrears of land revenue. Section 3(1)(d) contemplates that money payable to the State Government or the Corporation, under an

agreement, is recoverable as arrears of land revenue, if conditions contemplated therein are satisfied.

10. In the present case, the agreement which has been relied upon by the respondents contained no stipulation or clause that any sum due

thereunder can be recovered as arrears of land revenue. In the absence of there being any provision in law or agreement for recovery of

contractual due being realizable as arrears of land revenue, the contractual due cannot be realized as arrears of land revenue. Learned counsel for

the petitioner has relied upon a Division Bench of this Court in Mohammad Umar Vs. The Collector/District Magistrate, The Tehsildar, Zila

Parishad, wherein after noticing the relevant provisions of the U.P.Z.A. & L.R. Act, it has been held that contract money for realization of

Tehbazari dues cannot be recovered as arrears of land revenue. Various other judgments on the point having been relied upon.

11. In view of the discussions made above, we find that issuance of recovery citation against the petitioner for realization of the contractual dues,

alleged to be payable by the petitioner as arrears of land revenue, is contrary to law. The citation issued on 8.11.2013 calling upon the petitioner to

pay the amount, therefore, is wholly without jurisdiction and is liable to be quashed.

12. The writ petition, therefore, succeeds and is allowed. Impugned recovery citation dated 8.11.2013 (Annexure No. 7 to the writ petition)

issued by respondent no. 3 is quashed. However, it would be open for the respondents to proceed in accordance with the terms of the contract for

determination of petitioner''s liability and its recovery, if any, in accordance with law.

From The Blog
Supreme Court to Rule on Multi-State Societies in IBC Cases
Oct
25
2025

Story

Supreme Court to Rule on Multi-State Societies in IBC Cases
Read More
Supreme Court: Minors Can Void Property Sales by Guardians
Oct
25
2025

Story

Supreme Court: Minors Can Void Property Sales by Guardians
Read More