Sham Labhaya Vs Punjab State Electricity and Another

High Court Of Punjab And Haryana At Chandigarh 17 Sep 2008 C.W.P. No. 3457 of 2006 (2009) 1 ILR (P&H) 495 : (2009) 3 SLR 132
Bench: Division Bench
Result Published
Acts Referenced

Judgement Snapshot

Case Number

C.W.P. No. 3457 of 2006

Hon'ble Bench

M.M. Kumar, J; Jora Singh, J

Advocates

Ashwani Talwar, for the Appellant; H.S. Sran, for the Respondent

Final Decision

Allowed

Acts Referred

Punjab State Electricity Board (Revised Pay) Regulations, 1988 — Regulation 8

Judgement Text

Translate:

M.M. Kumar, J.@mdashThe Petitioner has approached this Court with a prayer for quashing order dated 17th January, 2006 (Annexure P. 5)

passed by Respondent No. 2 whereby the benefit of two increments granted to him vide order dated 15th January, 1991 has been reduced to one

increment.

2. Brief facts of the case are that the Petitioner joined as Upper Division Clerk in the office of Respondent Board on 31st June, 1974. He was

promoted/posted as Assistant Revenue Accountant/Circle Assistant on 19th July, 1985. He was further promoted as Internal Auditor on 6th June,

1995. In view of the time bound promotional scale scheme introduced by Finance Circular No. 17/90 vide order dated 15th January, 1991

(Annexure P. 1), the Petitioner was granted the time bound promotional scale on completion of 16 years service in the Board and accordingly two

annual increments were given to him. His pay was fixed in the scale of 1,800--3,200. At the time of grant of second promotional scale the

Petitioner was posted as Assistant Revenue Accountant with effect from 19th July, 1985 and continued to be the same after the grant of scale. He

was not actually promoted to any higher post nor he was assigned any higher responsibility. On 12th May, 2004 (Annexure P.2) the Respondent

board passed an order reducing the benefit of two increments granted to the Petitioner vide office order dated 15th June, 1991 to one.

Accordingly a consequential order was passed by fixing his pay with effect from 31st May, 1990. The order dated 12th May, 2004 was

challenged by the Petitioner in this Court by filing CWP No. 8773 of 2004 which was disposed of by this Court on 26th April, 2005. The Division

Bench while quashing order dated 12th May, 2004 directed the Respondents to pass a fresh order in accordance with law after hearing the

Petitioner. The Petitioner made a representation on 5th September, 2005 (Annexure P.4) which has been declined vide order dated 17th January,

2006 (Annexure P.5). The afore-said order is subject matter of challenge in the instant petition.

3. The stand taken by the Respondent Board in the written statement is that the Petitioner was already granted first promotion as Assistant

Revenue Accountant on 9th July, 1985 and therefore he was not entitled to the first time bound promotional scale. It is further stated that Petitioner

completed 16 years of service on 31st May, 1990. The Petitioner was promoted from the post of UDC to that of Assistant Revenue Accountant

on 9th July, 1985 in the pay scale of Rs. 620-- 1,200 which scale was revised to 1,800--3,200 with effect from 1st January, 1986. As the next

promotion from the post of Assistant Revenue Accountant is to that of Senior Assistant/Internal Auditor having the same pay scale of 1,800--

3,200 which is equivalent to the post of Assistant Revenue Clerk i.e. the lower post and therefore on completion of 16 years of Service on 31st

May, 1990 the Petitioner could not get second promotion. Therefore, according to the instructions dated 3rd September, 1993, the Petitioner was

entitled to only one increment whereas due to inadvertence he was granted two increments. The said mistake was rectified vide order dated 12th

May, 2004 (Annexure R2).

4. When the matter came up for hearing on 9th September, 2008, the following order was passed:

During the course of arguments it has transpired that the circular dated 3rd September, 1993 (Annexure R6) has placed reliance on another

circular to which reference has been made in para 3. On a close scrutiny, we find that the aforementioned circular is to be applied when an

employee is promoted to the next higher post and his pay is to be fixed in that scale. However, in the present case the Petitioner has been

promoted from the post of Upper Division Clerk to the post of Assistant Revenue Accountant who started getting the pay scale of 1,800--3,200

with effect from 1st January, 1986 which scale, he also becomes entitled to on 31st May, 1990 i.e. after completing 16 years of service. The

circular Annexure R6 cannot be applied to the case of the Petitioner as it talks of promotion to the next higher post i.e. promotion to the post

which carries pay scale higher than 1,800--3,200.

After hearing learned Counsel for the parties, we find that it would be appropriate if we asked the counsel for the Board to find out as to whether,

the Board is following the policy of passing such like orders, in all the cases or it is only an individual case. Mr. Sran shall obtain instructions in this

regard......

5. The learned Counsel for the Board could not point out any case of such a nature. Therefore, we proceed to dispose of the matter.

6. We have heard the learned Counsel for the parties at some length and have gone through the paper book with their able assistance. It is

admitted postition that on his posting from the post of UDC to that of Assitant Revenue Accountant on 9th July, 1985 the Petitioner was not

granted any increments in terms of Regulation 8 of the Punjab State Electricity Board (Revised Pay) Regulation, 1988 which would be admissible

to an employee on his promotion. The action of the Respondents in reducing the benefit of two increments to one increment is not sustainable in

view of the provisions contained in Para 3 of Finance Circular No. 17/90, dated 23rd April, 1990 which reads thus:

At the time of placement in the time bound promotional/devised promotional scale, the employee will be allowed promotional increment(s), as are

admissible on promotion under the provisions of Regulation 8 of the PSEB (Revised Pay) Regulations, 1988 and as amended from time to time.

7. It is thus evident that when the Petitioner was promoted from the post of Assistant Revenue Accountant to that of Senior Assistant/ Internal

Auditor on 6th June, 1995, his pay scale continued to be the same at 1,800--3,200. The Circular dated 3rd September, 1993 (Annexure P-6) has

not been correctly interpreted and applied to the case of the Petitioner. It would be necessary to read operative part of the Circular which is as

under:

In case an employee has already availed of the benefit of placement to the time bound promotional/devised promotional scale(s) and is promoted

to the next higher post, his pay would be fixed at the next stage in the same scale and his next date of increment will remain unchanged. In case, he

is promoted to a post which is lower than the scale in which he has already been placed on time bound promotional devised promotional scale; he

will not be entitled to anyincrement and continue to draw the pay of the scale in which he has already been placed.

8. A perusal of the afore-mentioned para would clearly show that in a case where an employee has already availed the benefit of placement to the

time bound promotional/devised promotional scale(s) and such an employee is promoted to the next higher post, then his pay would be fixed at the

next stage in the same scale without any change in the date of his increment. If the afore-mentioned provision is correctly applied to the Petitioner,

then it becomes evident that the Petitioner was granted the scale of 1,800--3,200 with effect from 9th September, 1986 which was the revised pay

scale of the post of Upper Division Clerk with effect from 1st January, 1986 and he also became entitle to be placed in that scale of 1,800---

3,200 on the completion of 16 years service on 15th January, 1991. He was further promoted to the post of Internal Auditor on 6th June, 1995 in

the same pay scale of 1,800-- 3,200. The Finance Circular No. 34/93, dated 3rd September, 1993, would not apply to the case of the Petitioner

as he has not been promoted and his pay scale continued to be Rs. 1,800--3,200 nor he was given the benefit of placement in the higher scale of

Rs. 1,800--3,200. Therefore, impugned order dated 17th January, 2006 (Annexure R5) passed by the Respondent No. 2, is not sustainable in the

eyes of law. We further find that the Circular dated 23rd April, 1990 was amended later on 3rd September, 1993 and the amendment does not

suggest that it is to operate retrospectively with effect from 23rd April, 1990. For this additional reason, we also find that any instruction contrary

to Circular dated 23rd April, 1990 issued at the hands of Respondents, in any case, cannot be applied to the case of the Petitioner.

9. In view of the above, the writ petition succeeds and the same is allowed. Order dated 17th January, 2006 (Annexure R5) is quashed.

Respondents are directed to release the difference of pay to the Petitioner within a period of two months from the date of receipt of certified copy

of this order.

From The Blog
Supreme Court to Rule on Multi-State Societies in IBC Cases
Oct
25
2025

Story

Supreme Court to Rule on Multi-State Societies in IBC Cases
Read More
Supreme Court: Minors Can Void Property Sales by Guardians
Oct
25
2025

Story

Supreme Court: Minors Can Void Property Sales by Guardians
Read More