NAVIN CHAWLA, J.
As the learned counsel for the respondent enters appearance on advance notice, the caveat stands discharged.Â
IA No. 4672-4673/2018(Exemptions)
Allowed, subject to all just exceptions.
ARB. A. (COMM.) 19/2018 & IA No. 4671/2018
1.Issue notice. Notice is accepted by Mr.Manoj K. Singh, Advocate on behalf of the respondent.
2.By way of the present appeal under Section 37 of the Arbitration and Conciliation Act, 1996, the appellant seeks to challenge the order dated
20.12.2017 passed by the Arbitral Tribunal in arbitration proceedings between the parties insofar as it directs the appellant to make a payment
corresponding to second annual Minimum Guaranteed Quantity (MGQ) within sixty days from the receipt of the order subject to the
respondent/claimant furnishing bank guarantees of equivalent amount as stipulated in the contract. The learned senior counsel for the appellant submits
that the above direction could not have been passed as an interim order as the same amounts to grant of final relief claimed by the respondent in its
Statement of Claim before the Arbitral Tribunal. He further draws my attention to Clause 7.3 of the contract to contend that the MGQ is to be
calculated for each completed year. He submits that in the present case, due to certain force majeure condition, the second year could not be treated
to have been completed and therefore, the direction passed by the Arbitral Tribunal is even otherwise incorrect and premature. He further submits
that though in Clause 7.3 of the agreement the MGQ is prescribed as 3MMT per annum of coal, the Ministry of Environment and Forest has given a
clearance of only 1.5 MMT per annum in favour of the appellant and therefore, the MGQ as provided in Clause 7.3 of the agreement has to be
revised accordingly. He further submits that the contract between the parties was terminated by the appellant by its notice dated 24.07.2017 and if the
force majeure condition is taken into account, the termination would have been effected in the second year of operation and accordingly the
respondent would not be entitled to the MGQ as provided in Clause 7.3 of the agreement.
3.I have considered the submissions made by the learned senior counsel for the appellant, however, I am unable to agree with the same. One of the
important aspects of this case is that for the first year of operation the respondent has made a similar plea for release of MGQ in its favour. The same
was granted by the Arbitral Tribunal in favour of the respondent on a similar condition of furnishing a bank guarantee by its order dated 15.07.2017.
The appellant, being aggrieved of the same, challenged the order before this Court by way of ARP. A. (COMM.) 28/2017. The same was dismissed
by this Court by its order dated 25.10.2017. The appellant thereafter, challenged the said order before the Supreme Court by way of Special Leave
Petition to Appeal (c) No. 35103/2017, however, the same was also dismissed by order dated 09.01.2018. In my opinion, the plea raised by the learned
senior counsel for the appellant is an attempt to have a second bite of the cherry. All pleas raised by the appellant have already been considered by
the Arbitral Tribunal, by this Court and even by the Supreme Court in its earlier orders. The appellant cannot be allowed to re-agitate the same issues
second time over.
4.As far as the plea of force majeure is concerned, Clause 7.3 of the agreement, which has been relied upon even in the earlier orders passed by the
Arbitral Tribunal and by this Court, clearly provides that no dispute raised by the appellant would be valid until the appellant has made the payment of
the MGQ pursuant to the sub-Clause(c) of Clause 7.3 of the agreement, that is the entire MGQ amount. It is also noted that the appellant is fully
secured against the said payment by way of bank guarantees provided by the respondent in terms of Clause 7.3 itself.Â
5.As far as the plea of termination of the agreement is concerned, the second year of operation, as pointed out by the counsel for the respondent
ended on 14.06.2017. The termination notice is issued on 24.07.2017. Whether the force majeure condition can have the effect of extension of the
second year of operation or not, will be a question to be determined by the Arbitral Tribunal and cannot be considered today to scuttle the effect of
Clause 7.3 of the agreement. This would be one of the disputes that the appellant can raise in terms of Clause 7.3 of the agreement itself, however,
only after paying the MGQ amount in terms of the said Clause.Â
6.As far as the reliance of the appellant on the order passed by the Ministry of Environment and Forest is concerned, I may only note that a similar
plea raised by the appellant in relation to the first year of operation has been rejected by the Arbitral Tribunal and also by this Court by detailed
order(s) and an SLP challenging the same also stands rejected by the Supreme Court. In my opinion, the appellant cannot be allowed to raise the said
plea repeatedly only because the order now passed relates to the second year of operation.Â
7.The learned senior counsel for the appellant submits that the appellant would be separately challenging the order passed by the Arbitral Tribunal
insofar as the Impugned Order has granted a stay on the termination notice issued by the appellant. Both the parties would be at liberty to raise all
submissions and contentions in this regard as and when such appeal is filed.
8.In view of the above, I find no merit in the present appeal and the same is accordingly dismissed, with no order as to costs.       Â