NICCO Corporation Ltd. Vs Cable Corporation of India Limited and Others

Calcutta High Court 15 Oct 2007 M.A.T. No. 2550 of 2007 with C.A.N. No. 7170 of 2007 (2008) 1 CHN 567 : (2008) 2 CTLJ 321 : 112 CWN 341
Bench: Division Bench
Acts Referenced

Judgement Snapshot

Case Number

M.A.T. No. 2550 of 2007 with C.A.N. No. 7170 of 2007

Hon'ble Bench

Bhaskar Bhattacharya, Acting C.J.; Rudrendra Nath Banerjee, J

Advocates

Anindya Kumar Mitra, Abhrajit Mitra, S.N. Pyne and Jishnu Chowdhury, for the Appellant;Dipak Kumar Basu and Aparna Banerjee, Saktinath Mukherjee, Bhaskar Ghosh, Pallab Kumar Chakraborty and Sandipan Mitra, for the Respondent

Acts Referred

Constitution of India, 1950 — Article 12

Judgement Text

Translate:

Bhaskar Bhattacharya, ACJ.

1. These two mandamus appeals were heard together as these are preferred against the self-same order dated 6th August, 2007 passed by a

learned Single Judge of this Court by which His Lordship allowed a writ application filed by the Universal Cable Ltd. the private respondent in

these appeals, by setting aside the decision of the Metro Railway Authority to award contract in favour of NICCO Corporation Limited

(""NICCO""), the appellant, in one of these appeals with the observation that whatever amount of work had already been executed by NICCO

should not be undone and it would be entitled to the payment as per its entitlement for the work done till the date of delivery of judgment. His

Lordship, however, directed the Metro Railway Authority to proceed to award the contract for the balance work to the next eligible tenderer or to

initiate fresh process for execution of the balance work with further direction that in such a case, NICCO would not be entitled to participate in the

process of fresh tender.

2. Being dissatisfied, both the NICCO and the Metro Railway Authority have preferred these two separate appeals.

3. The Universal Cable Limited, the private respondent before us in these two appeals, filed a writ application before the learned Single Judge

thereby praying for the following relief:

(a) A writ in the nature of Mandamus commanding the respondent Nos. 1 and 2 to complete the tendering process in term of the notice of tender

No. ELECTVC/GARIA/2/R for supply erection/laying and commissioning of 33KV and 11 KV Feeder Cables from Shayam Bazar RSS to New

Garia TSS for power supply arrangement in Tollygunge-Garia section and the price bids submitted by successfully awarding the work contract in

favour of the consortium of the petitioners being the only eligible bidder;

(b) A writ in the nature of Mandamus commanding the respondent Nos. 1 to 2 to strictly act in terms of the terms and conditions of the tender

advertisement published in April, 2006 and in terms of the General Condition of tender and conditions of contract of the Electrical Engineering

Department, Metro Railway, Calcutta;

(c) A writ in the nature of Certiorari commanding the respondent authorities to transmit all records in respect of the said tendering process and

upon failure to show cause and/or reasonable cause to quash the same;

(d) Rule NISI in terms of prayers (a), (b) and (c) above;

(e) Interim order restraining the respondent authorities from awarding the work contract and/or cancelling the tendering process without leave of

this Hon''ble Court and/or until disposal of the writ petition;

(f) Ad interim prayers in terms of prayer (e) above;

(g) Any other or further order or orders as to Your Lordships may deem fit and proper.

3a. The case made out by the writ petitioner may be summed up thus:

(1) The writ petitioner entered into a consortium agreement for the purpose of making consortium bid and entering into a contract for supplying,

laying, erection, testing and commissioning of 11KV and 33KV power cables in Tollygunge and Garia Section against the tender issued by the

Metro Railway Authority.

(2) In the month of October, 2005, the respondent No. 2, on behalf of the President of India* issued a notice of tender inviting open tender in

sealed cover from the reputed licensed contractors for the work of supply of erection/laying and commissioning of 33KV and 11KV feeder cables

from Shyam Bazar RSS to New Garia TSS for power supply arrangement in Tollygunge-Garia section with a period of completion of 24 months

from the date of issue of letter of agreement. The total estimated value of the work was Rs. 23,15,80,178/-.

(3) In response to the above tender notice, the writ petitioners submitted their Techno Commercial Bid and the Price Bid along with other

contractors. Although, the Techno Commercial Bids of the bidders were opened, the Metro Railway Authority, for the reason best known to

them, cancelled the tender notice and the tender evaluation process. The Deputy Chief Electrical Engineer, on behalf of the respondent No. 2,

intimated the writ petitioner No. 1 that the subject tender had been discharged by the competent authority; however, no reason was assigned, in

the said letter.

(4) After a gap of six months, the respondent authorities issued a fresh notice of tender in the month of April, 2006 for the self-same work, which

was the subject-matter of the former tender issued in the month of October, 2005.

(5) The estimated value, eligibility criteria and other terms and conditions of the subsequent tender were the same as that of the earlier tender.

(6) The writ petitioners in response to the above notice of tender issued in the month of April, 2006 again submitted its price bid within the due

date on August 4, 2006.

(7) There were six bidders for the subsequent tender and after evaluation of the Techno Commercial Bids, which were opened on August 4, 2006,

three bidders namely, Yamuna Gases and Chemicals Limited, NICCO Corporation Limited and the writ petitioners were shortlisted for evaluation

of price bids, which were opened on 10th October, 2006. The Yamuna Gases and Chemicals Ltd. submitted only variable price bid and therefore,

became ineligible in view of the withdrawal of the variable price by the respondent authorities and, thus, effectively the other two bidders submitted

firm price bid and were within the zone of consideration.

(8) NICCO Corporation Ltd. quoted for 81.215% increase on the estimated tender value of Rs. 23,15,80,178/- whereas the writ petitioners

quoted for 120.824% increase on the estimated tender value.

(9) On cancellation of the first tender, on 18th April, 2006, it was intimated by the Metro Railway Authorities that the job should be retendered.

After about five months, the subsequent tender was floated. In the meantime, there was unprecedented rise in the price of copper all over the

world, which is the main raw material for manufacturing the cables involved in the tender and it constituted approximately 75% of the raw material

cost. Surprisingly enough, the Metro Railway Authorities while re tendering the work in April, 2006 did not at all take into consideration the

increased copper-price and did not re-estimate the value of the revised tender and thereby, diluting the eligibility criteria of the subsequent tender.

(10) NICCO Corporation Ltd. was ineligible for participation in the tendering process vide notice of tender published in the month of October,

2005 in view of the fact that it was one of the essential eligibility criteria that the intending tenderer should have completed in the last three financial

years from 2002-03, 2003-04, 2004-05 and 2005-06 till the date of opening of the tender at least one similar single work involving supply,

erection, testing and commissioning work of power cables/traction sub-station/power supply sub-station/power supply transmission including its

protection scheme for system voltage of 11KV/33KV and/or above for a minimum value of 35% of the advertised tender value of work.

(11) The respondent authorities cancelled the previous notice of tender published in the month of October, 2005 and a fresh tender in the month of

May, 2006 on the self-same terms and conditions was issued only to give work order in favour of NICCO Corporation Ltd., which in the

meantime, managed to gather the experience in terms of Clause (b) of the eligibility criteria for the purported completion of work contract in

January, 2006.

(12) The memo dated 22nd May, 2006 issued by the Karnataka Power Transmission Corporation Ltd. in favour of NICCO Corporation Ltd.,

which was commissioned only in January, 2006, was invalid and on the basis of such certificate no work order could be given.

(13) The said Karnataka Power Transmission Corporation Ltd. had de-listed NICCO Corporation Ltd. from its approved list of companies

involving 66KV underground cables but in spite of such fact, Metro Railway Authorities selected the NICCO Corporation Ltd. being the lowest

bidder. Hence, the writ application.

4. The NICCO Corporation Ltd. contested the application thereby opposing the prayer of the writ petitioner and contending that it had the

requisite eligibility criteria for the tender in question and being the lowest bidder, the Metro Railway Authorities rightly issued the work order in its

favour.

5. The Karnataka Power Transmission Corporation Ltd. by filing affidavit more or less supported the claim of the NICCO Corporation Ltd. that it

had completed its work under the said corporation, but it was made clear that the certificate relied upon by the NICCO was not the performance

certificate.

6. The Metro Railway Authorities also justified their action and opposed the writ application.

7. The learned Single Judge by the order impugned herein although did not accept the allegation of the writ petitioner that the previous notice of

tender was cancelled to accommodate the NICCO Corporation Ltd., found substance in the plea of the writ petitioner that the NICCO

Corporation Ltd. had no requisite eligibility as the certificate issued by the Karnataka Power Transmission Corporation Ltd. merely indicated

completion of the project and that the same was not the certificate of performance and according to the learned Single Judge, existence of the

performance certificate in favour of the bidder was essential in order to be eligible for the said contract.

8. As in the meantime, about 80% of the work had already been completed. His Lordship directed the Metro Railway Authorities not to give

further work order with added direction that either the balance work should be done through the next eligible bidder or the Metro Railway

Authorities would be free to issue fresh process of tender. His Lordship, however, made it clear that in case of fresh tender, NICCO would not be

entitled to participate. His Lordship further directed the Metro Railway Authority to pay costs of Rs. 50,000/- to the writ petitioners with liberty to

realise such amount from the persons who were responsible for selecting NICCO.

9. As indicated earlier, being dissatisfied, these two appeals have been preferred, one by the NICCO Corporation Ltd. and other, by the Metro

Railway Authorities.

10. Mr. Mitra, the learned Senior Advocate appearing on behalf of the NICCO Corporation Ltd, has strenuously contended before us that the

learned Single Judge having turned down the principal allegation of the writ petitioner i.e. mala fide against the Metro Railway Authority and arrived

at the conclusion that the rejection of the previous notice of tender was made on just ground, the case of the writ petitioner fails as his client had the

required eligibility criteria. According to Mr. Mitra, the finding of the learned Single Judge that filing of performance certificate was an essential

condition for the tender was unreasonable and even the writ petitioner could not file such performance certificate along with its tender papers. Mr.

Mitra contends that the techno commercial bids of the parties were opened on August 4, 2006 and as such, the writ petitioner was quite aware of

the qualification of the parties to the bid but filed the writ application on January 19, 2007, after the work order was issued in favour of his client.

Such fact, Mr. Mitra continues, indicates that all the parties proceeded as if performance certificates were not required to be given. Mr. Mitra

points out that the writ petitioner even could not raise such objection because in such a situation, its own bid would have also been rejected. Mr.

Mitra further contends that the writ application should have been rejected on the ground of delay alone as the work order had already been issued

in favour of his client. Mr. Mitra further contends that having regard to the fact that at the time of disposal of the writ application, 80% of the work

having been completed by his client. His Lordship should not have interfered at that stage when admittedly the parties proceeded as if both the

bidders were eligible and the writ petitioner, itself, could not file any performance certificate. Moreover, the writ petitioner having participated at

the process of selection and having failed on merit, its bid being higher by several crores of rupees, it had no right to maintain the writ application

when it had also not filed the performance certificate in support of its qualifications. Mr. Mitra further contends that there was even no justification

of restraining his client from participating in the fresh tender when His Lordship did not restrain the writ petitioner, similarly placed with the

appellant, from participating in the fresh process of tender. Mr. Mitra, therefore, prays for setting aside the order passed by the learned Single

Judge and allowing the appeal.

11. Mr. Basu, the learned Advocate appearing on behalf of the Metro Railway Authority, the appellant in the other appeal, has adopted the

submissions of Mr. Mitra and in addition to those, has contended that in view of the order passed by the learned Single Judge the railway project

has suffered a serious set back as 80% of the work had already been completed. Mr. Basu submits that satisfactory completion of a work does

not necessarily mean that the production of performance certificate was necessary at the stage of considering the bids. Mr. Basu further points out

that the bid of the writ petitioner being Rs. 9 crore more than that of the appellant, his client accepted the bid of the NICCO as both were

technically competent to get the work order. Mr. Basu, therefore, prays for setting aside the order passed by the learned Single Judge.

12. Mr. Mukherjee, the learned Senior Advocate appearing on behalf of the writ petitioner has supported the conclusion arrived at by the learned

Single Judge and in addition, has submitted that the issue of mala fide raised by his client ought to have been decided against the railway authority.

According to Mr. Mukherjee, the client of Mr. Mitra having failed to acquire the essential eligibility criterion of successful completion of a similar

work the learned Single Judge rightly allowed the writ application. Mr. Mukherjee further contends that in view of the admitted fact that the price

of copper, the main ingredient of the work material, having been increased during the relevant period, the railway authority at the time of issuing the

fresh tender in the month of April, 2006 ought to have increased the value of the project but with mala fide intention, did not enhance such

valuation lest Mr. Mitra''s client would lose the opportunity to participate for want of eligibility criteria. Mr. Mukherjee, therefore, prays for

dismissal of these appeals on further ground that there was unholy connection between the two appellants before us.

13. Therefore, the first point that arises for consideration in this appeal is whether filing of performance certificate for doing the similar job within

the period mentioned in the notice of tender was a necessary qualification of the bidders.

14. The notice of tender lays down the following eligibility criteria for the bidders:

a) Total contract amount received during the last three financial years and in the current financial year should be minimum of 150% of advertised

tender value.

b) The intending tenderer should have completed in the last three years (i.e. current year and three previous financial years i.e. 2003-04, 2004-05,

2005-06 and in 2006-07 till the date of opening of the tender) and at least one similar work involving ""supply, erection, testing and commissioning

work of power cables/transaction sub-station/power supply sub-station/power supply transmission, including its protection scheme of system

voltage of 11KV/33KV and/or above"" for a minimum value of 33% of the advertised value of work.

c) The intending tenderer shall have to produce revenue/banker''s solvency certificate of 40% of the advertised tender value.

Notes appended to the tender notice gave following indication as regards criterion (b):

The word completed means having satisfactorily executed the work of requisite value in the qualifying period specified in criterion (b) above, as

regard similar work the tenderer should have satisfactorily executed one work for supply, erection, testing and commissioning work of power

cables/traction sub-station/power supply transmission, including its protection scheme for voltage of HKV/33KVand/or above of at least 35% of

the advertised tender value of work in the prescribed period.

14a. The certificate produced by the NICCO shows that the Karnataka Power Transmission Corporation has given the following certificate issued

by the Executive Engineer of the Corporation:

This is to certify that M/s. NICCO CORPORATION LTD, Cable Division, Kolkata have executed Design, Manufacture, Testing, Supply of

66KV station at MRS to Telecom Layout in Vijaynagar, Bangalore.

This job was carried out against DWA No. 208-210 dated 18.6.2003. This cables were tested and commissioned on 4.1.2006 and the

performance is satisfactory.

15. According to the writ petitioner, the said certificate is not a certificate of performance but a mere completion certificate and according to the

terms of agreement between the NICCO and the Karnataka Corporation, the performance certificate can only be issued by the Chief Engineer

and not by the Executive Engineer.

16. At this stage, it would be profitable to refer to the certificate dated 3.11.05 relied upon by the writ petitioner in support of its bid, which is

quoted below:

To whom it may concern.

Sub: Payment Certificate

Ref: Supply and installation package of 132KV Cable from Gaighat Sub-Station along Mahatma Gandhi Setu up to Hazipur end of the bridge.

M/s. CCI Limited was awarded the Work, of 132KV XLPE Cable Lying across Mahatma Gandhi Setu over river Ganga from BSEB, Grighat

Sub-Station, Patna to Cable termination yard at Terasia Maidan (6.774KM) vide LOA No. C-45708-1 399-3/LOA-1/1213 date 08.01.04

(supply portion) and LOA No. C-45708-1399-3/LOA-11/1214 dated 08.01.04 (erection portion). Total value of work was Rs. 28.8 cr. The

work has been completed successfully on 26.04.05 and the entire payment has been made to M/s. CCI Limited.

17. After going through the two certificates relied upon by the parties, we find that those certify ""successful completion"" of the work but none of

those certificates can be said to be ""performance certificate"". The fact that entire payment has been made does not imply that the guarantee period

of performance was over and to that effect, no certificate was issued to the writ petitioner.

18. The parties, however, including the Metro Railway Authority, all along proceeded as if production of successful completion certificate by the

bidders was sufficient to be eligible in the process of tender and as such, no objection was raised by the writ petitioners at the time of opening of

the techno commercial bid on August 4, 2006 and only in its letter dated December 6, 2006, after the price bids had been opened and it has been

disclosed that the writ petitioner was not the lowest bidder, the writ petitioner for the first time complained that the words ""satisfactorily executed

would mean ""performance of a contact till the guarantee/warranty period was over"". It does not appear from the record that any other bidder''s bid

was rejected for non-supply of performance certificate. As it appears from the record that there were six bidders who initially participated but

three out of them were disqualified at the opening of the techno commercial bid and the other three including the writ petitioner and the NICCO

were in the process of contest. At that point of time, the writ petitioner did not raise any objection as regards the eligibility of the NICCO for non-

submission of the performance certificate as the parties proceeded that filing of such certificate was not necessary.

19. In our view, the plain reading of the conditions of tender do not indicate that the parties were called upon to produce ""performance certificate

of their past work, which can only be obtained after the expiry of the period of guarantee of performance fixed by the agreement was over. If the

object of the railway was to get the performance certificate from the bidders at the time of submission of the bids, it would not have asked them to

produce even the performance certificate for the work done in the current year viz. 2006-07 till the date of opening of the tender when the

advertisement was given in the month of April, 2006, the last date of submission of tender was June 1, 2006, and the self-same day was the date

for opening the tender except the price bid (as appearing from the notice printed at page 69 of the paper-book) knowing fully well that it was

impossible for any bidder to get such performance certificate for the work done during the year 2006-07 till the date of opening of the tender.

Therefore, in our opinion, it was rightly contended on behalf of the railway authority that it intended that the completion certificate was sufficient to

meet the eligibility criteria and the parties proceeded on that basis without raising any objection. It is now settled law that when two interpretations

of a clause of a notice of tender are possible and the tendering authority has adopted one of those, which is not an absurd view, a Writ Court

should not interfere with the decision of the authority. The learned Single Judge, as it appears from the order impugned, was impressed by the fact

that in Form V of the tender papers there was an item for production of the performance certificate and according to His Lordship, such clause in

the tender paper justified the contention of the writ petitioner that the performance certificate should have been filed. With great respect, we are

unable to subscribe to the view taken by His Lordship. In our opinion, the terms of a tender should be interpreted, on the basis of the requirement

indicated in the advertisement of the tender particularly when such advertisement has explicitly, disclosed the eligibility criteria including their

explanation. If some new clause is added in the tender paper which is inconsistent with the conditions mentioned in the advertisement, such

inconsistent clause in the tender papers should be ignored unless fresh corrigendum is issued regarding the eligibility criteria. In our view, it is rightly

contended by Mr. Mitra, the learned Counsel for the NICCO that the said Form V was merely a checklist for the purpose of verification of the

papers submitted by the bidders and the expression ""performance certificate"" has been loosely used but never with the intention of meaning ""the

document certifying that the previous project completed by the bidder had performed satisfactorily during the guarantee period agreed to by the

parties"" and consequently, the said expression in the tender paper cannot have overriding effect on the terms mentioned in the advertisement.

20. Over and above, in the case before us, the writ petitioner itself having the same deficiency, even if we assume for the sake of argument that

production of performance certificate was compulsory, none of the rights of the writ petitioner has been infringed by the alleged wrong decision of

the tendering authority as its bid has not been cancelled on that ground but his bid was rejected as it was higher one by huge amount of Rs. 9 crore

and odd. The position would have been different if the railway authority had rejected the bid of the writ petitioner on the ground of non-submission

of performance of certificate but ignored the same defect of the NICCO and in such a situation, the writ petitioner could have reasonably argued

that he had been discriminated.

21. We, therefore, hold by relying upon the decision of the three-Judges Bench of the Apex Court in the case of Om Prakash Shukla Vs. Akhilesh

Kumar Shukla and Others, , that if a party has taken a chance of selection without protest but remained unsuccessful on merit, he cannot be

permitted to challenge the process of selection on the ground of some illegality even if we assume for the sake of argument that filing of

performance certificate was an essential condition. The learned Single Judge, in this connection, has relied upon the following observations of a

three-Judges Bench in the case of Raj Kumar and Others Vs. Shakti Raj and Others, , which is also reported in Raj Kumar and Others Vs. Shakti

Raj and Others, :

Yet another circumstance is that the Government had not taken out the posts from the purview of the Board, but after the examinations were

conducted under the 1955 Rules and after the results were announced, it exercised the power under the proviso to para 6 of 1970 notification and

the posts were taken out from the purview thereof. Thereafter the Selection Committee was constituted for selection of the candidates. The entire

procedure is also obviously illegal. It is true, as contended by Shri Madhava Reddy, that this Court in Madan Lal and Others Vs. State of Jammu

and Kashmir and Others, and other decisions referred therein had held that a candidate having taken a chance to appear in an interview and having

remained unsuccessful, cannot turn round and challenge either the constitution of the Selection Board or the method of selection as being illegal; he

is estopped to question the correctness of the selection. But in his case, the Government have committed glaring illegalities in the procedure to get

the candidates for examination under 1955 Rules, so also in the method of selection and exercise of the power in taking out from the purview of

the and also conduct of the selection in accordance with the rules. Therefore, the principle of estoppel by conduct or acquiescence has no

application to the facts in this case. Thus, we consider that the procedure offered under the 1955 Rules adopted by the Government or the

committee as well as the action taken by the Government are not correct in law.

22. It is apparent that the said Bench did not dispute the proposition of law enunciated in the case of Om Prakash Shukla (supra) reiterated in the

case of Madan Lai (supra), but having regard to the fact that in the said case, the Government made ""glaring"" illegalities in the procedure of

selection and the State decided to withdraw the appeals at the hearing stage and at the same time, the Apex Court permitted other various

interveners to participate, the litigations really took the shape of a Public Interest Litigation as several appeals were heard and disposed of by the,

said order and consequently, the Bench did not reject the writ application on the ground of estoppel. Therefore, the said decision cannot be cited

as precedent for the purpose of nullifying the effect of the well-settled proposition of law laid down by a Bench of equal strength. We find that for

doing complete justice between the parties, the Supreme Court, in that case, did not apply the doctrine of estoppel in the facts of the said case.

23. The learned Single Judge also relied upon the decision of the Supreme Court in the case o Ramana Dayaram Shetty Vs. International Airport

Authority of India and Others, , in holding that when a ""state"" entertains the tender of a party even though it does not have the requisite experience,

it denies equality of opportunity to others similarly situated in the matter of tendering for the contract and there may have been many others who

were precluded from participating in the tender as a result of conditions of eligibility mentioned in the advertisement of contract. In our opinion, the

said decision is not applicable to the fact of the present case for two reasons. First, we have already held that the terms of the tender did not

require the filing of performance certificate and secondly, even if we hold otherwise for the sake of argument, in the case of Ramanna (supra), the

appellant did not participate in the process of tender under the impression that he having no qualification as mentioned in the notice of tender, his

bid would be rejected but filed the writ application, challenging the selection on the ground that if he knew that the eligibility criteria mentioned in

the notice of tender would not be strictly applicable he would have applied and in such circumstances, objection was raised that at his instance the

writ application was not maintainable as he did not participate in the process of tender. The Supreme Court rejected such plea by making the

following observations:

That takes us to the next question whether the acceptance of the tender of the 4th respondent was invalid and liable to be set aside at the instance

of the appellant. It was contended on behalf of the 1st and the 4th respondents that the appellant had no locus standi to maintain the writ petition

since no tender was submitted by him and he was a mere stranger. The argument was that if the appellant did not enter the field of competition by

submitting a tender, what did it matter to him whose tender was accepted; what grievance could he have if the tender of the 4th respondents was

wrongly accepted. A person whose tender was rejected might very well complain that the tender of someone else was wrongly accepted, but, it

was submitted, how could a person who never tendered and who was at no time in the field, put forward such a complaint? This argument, in our

opinion, is misconceived and cannot be sustained for a moment. The grievance of the appellant, it may be noted, was not that his tender was

rejected as a result of improper acceptance of the tender of the 4th respondent, but that he was differentially treated and denied equality of

opportunity with the 4th respondent in submitting a tender. His complaint was that if it were known that non-fulfilment of the condition of eligibility

would be no bar to consideration of a tender, he also would have submitted a tender and competed for obtaining a contract. But he was precluded

from submitting a tender and entering the field of consideration by reason of the condition of eligibility, while so far as the 4th respondent was

concerned, their tender was entertained and accepted even though they did not satisfy the condition of eligibility and this resulted in inequality of

treatment which was Constitutionally impermissible. This was the grievance made by the appellant in the writ petition and there can be no doubt

that if this grievance were well founded, the appellant would be entitled to maintain the writ petition. The question is whether this grievance was

justified in law and the acceptance of the tender of the 4th respondent was vitiated by any legal infirmity.

(Emphasis supplied)

24. Here the position is otherwise. The writ petitioner understood the terms of the contract and participated without raising any protest as regards

the production of performance certificate because he knew that if such objections were raised, he would be out of the process. After opening of

the techno commercial bid, three out of six bidders were eliminated for want of eligibility but the writ petitioner did not dispute the qualification of

the NICCO. After opening of the price-bid, when his bid was found to be higher by Rs. 9 crore and odd than that of NICCO, the selected bid, he

raised objection regarding the necessity of filing of performance certificate. As the bid of the writ petitioner was not cancelled on the ground of

non-submission of performance certificate but was not accepted because of higher amount of bid, he cannot be prejudiced in any way by the

decision of the tendering authority and the principles, laid down in the case of Om Prakash (supra), is clearly applicable.

25. Similarly, we do not find any substance in the contention of Mr. Mukherjee, the learned Advocate appearing on behalf of the writ petitioner

that the Metro Railway Authority ought to have enhanced the value of the tender for the increase of price of copper within the period of six months

and that it did not increase the value because in such a case, the NICCO would not get the qualification for bidding. It is rightly contended by Mr.

Basu and Mr. Mitra, the learned Counsel appearing on behalf of the appellants that railway would try to minimise the costs of construction and that

there was no reason of unnecessarily enhancing the value of the work at the cost of public exchequer. The writ petitioner, as it appears from

record, after the opening of the price bid, for the first time in writing complained of such objection of valuation alleging that such point was agitated

during pre-bid discussion on May 22, 2006. We fail to appreciate why such point was not raised in writing earlier and accordingly, we turn down

such absurd contention. We have already pointed out that the railway authority rightly refused to increase the value of the tender work from the

one, which was fixed just six months earlier. It is true that in the letter dated June 28, 2006, the writ petitioner complained of price-hike of copper

but its complaint was against the withdrawal of price variation clause; in the said letter, it never complained of mala fide motive of Railway

Authority in protecting the NICCO from disqualification by not enhancing the valuation of the work order.

26. The next question is whether the writ application was liable to be dismissed also on the ground of delay.

27. In this case, the work order was issued on January 5, 2007 and the writ application was filed on January 17, 2007. However, the application

was listed for the first time on February 16, 2007 and was moved on February 22, 2007 when a learned Single Judge passed direction for filing

affidavits but the prayer for interim order was refused.

28. The learned Single Judge by the order impugned held that the writ application having been affirmed 12 days after the issue of the work order,

there was no delay. In arriving at the conclusion. His Lordship held that the writ petitioner prior to issue of the work order in favour of the NICCO

had raised objection regarding the ineligibility of the NICCO to participate in the process of tender and could have approached the Writ Court

being aggrieved by the inaction by the Metro Railway Authority to consider such objection and to pass an order thereon in one way or the other;

however, according to His Lordship, the contract in favour of the NICCO not having been awarded, and the petitioners having been assured of

consideration of their objection, any writ application prior to issue of the work order in favour of the NICCO would run the risk of being rejected

as premature and only after the work order was issued that a right had accrued in favour of the writ petitioner.

29. We have already pointed out that prior to opening of the price-bid, the writ petitioner never complained of ineligibility of the NICCO in writing

although the eligibility bid was opened earlier and we have not found any written document issued by the Metro Railway Authority assuring the writ

petitioner of considering any objection of ineligibility of the NICCO for not filing the performance certificate or the enhancement of valuation of the

work order. It is preposterous to suggest that after a notice of tender had been issued, the last date of submission of bids expired, bids submitted,

the techno commercial bids opened and even the price bids had been considered, there was any lawful scope of giving any assurance at the

instance of a ""State"" within the meaning of Article 12 of the Constitution of India to any of the bidders of enhancing the valuation of the work order

for the purpose of eliminating the lowest bidder from the process of tender on the ground of want of eligibility criteria. Therefore, the plea taken by

Mr. Mukherjee is an absurd one. After the techno commercial bid was opened and some of the bidders were eliminated, there was no scope of

giving any assurance to the writ petitioners of further excluding any of the remaining bidders on the ground of ineligibility.

30. We find from the work order that the successful bidder was required to take steps immediately for giving bank guarantee and to contact the

railway authority by 10 days after receiving the letter for further action and direction for execution of the work. The work order was valued about

Rs. 37 crore and therefore, for supply of material, the successful bidder is required to take immediate step not only for procuring money but also

for preparation of the work.

31. In our view, merely because a writ application was affirmed within 12 days from the issue of the work order, such conduct on the part of the

writ petitioner is not sufficient to get rid of any allegation of laches and delay. So long the writ application was not moved before the Court and the

Court after beingpnma facie satisfied calls for affidavit from the respondents, the successful bidder is not required to give importance of any such

writ application and even can allege mala fide against the writ petitioner for deliberately not moving the same. We have already pointed out that

when the writ application was moved on 22nd February, 2007, by that time the successful bidder has started functioning pursuant to that order as

would appear from the letter dated February 15, 2007 written by the Metro Railway Authority that it had informed the NICCO the place for

storing of the materials and asked to pre-pone the date of inspection before 15thMarch, 2007.

32. It appears from the earlier letter dated 12th February, 2007 written by the NICCO to the Metro Railway Authority that they had planned to

supply 23 Kms. of 33KV. 1C x 185 sq. mm. cable by 20th March, 2007 and further 22 Kms. by 31at March 2007.

33. From those documents, it is clear that prior to the actual moving of the writ application, the NICCO had already taken step in accordance with

the work order and invested money for the purpose of complying with the terms of the huge job.

34. In our view, the learned Single Judge was not justified in only taking into consideration the fact that the writ petitioner affirmed the writ

application within 12 days from the date of passing of the work order. His Lordship ought to have taken note of the fact that mere filing of the writ

application without making any endeavour to move the same in the facts of the present case cannot absolve it of the charge of inaction and in such

a case, the delay in moving the application is vital, inasmuch as, it can be reasonably concluded that the writ petitioner had with evil motive

deliberately allowed the successful bidder to spend money for performance of the job without actually moving the matter before the Court.

35. Moreover, during the pendency of the writ application, no interim order was granted in favour of the writ petitioner and when the matter came

up for final hearing, as it appears from the order impugned, 80% of the work had already been completed. Such fact should also be taken into

consideration at the time of disposal of the writ application. Since the work order was issued for public utility service and 80% work had already

been completed, in our view, the learned Single Judge should have also taken into consideration such fact even if we assume for the sake of

argument that production of performance certificate was a necessary condition of acceptance of the bid inasmuch as the cancellation of the work

order at that stage would cause huge delay in completion of a public project. The learned Single Judge ought to have considered the fact that for

the balance 20% of the work the completion of the project will be stalled and fresh advertisement is to be given for re-tender and in the process

the cost of the project will also be increased.

36. Apart from the question of delay, we find that the bid of the writ petitioner was more than nine crore of rupees higher than that of NICCO.

Cost of a construction is also a vital factor, which weighs with the public utility service authority in the matter of grant of work order. It appears

from the record that NICCO in the past had done this type of job and, therefore, this is not a case where the work has been done by a person

having no experience of this type of job. We have already found that successful completion of a project of a similar nature as mentioned in the

advertisement was the essential qualification and not the production of performance certificate and, therefore, in the facts and circumstances of the

present case the learned Single Judge should not have set aside the work order.

37. We also do not approve the further direction of the learned Single Judge that in future tender the NICCO should not be permitted to

participate whereas no such restriction was imposed upon the writ petitioner. If according to the learned Single Judge, the NICCO was not eligible

to apply for tender without having any performance certificate, the writ petitioner is equally ineligible and in such a case, the writ petitioner should

also be restrained from participating in the future process.

38. Be that as it may, in view of our specific finding that the filing of performance certificate, which can only be obtained after completion of the

agreed and the guaranteed period of successful performance of a project, was not the essential condition, the writ application is rejected with the

finding that there was no illegality in the process of selection of NICCO and that the approach of the writ petitioner was a mala fide one in the facts

of the present case as discussed above. The appeals are, therefore, allowed with costs, which we assess at Rs. 50,000/- each, separately to be

paid by the writ petitioners to the two appellants. The order impugned is set aside.

Rudrendra Nath Banerjee, J.

I agree.

From The Blog
SC: Brother Can Sell Father’s House Even Without Share
Oct
31
2025

Story

SC: Brother Can Sell Father’s House Even Without Share
Read More
SC to Decide If Women Can Face POCSO Penetrative Assault
Oct
31
2025

Story

SC to Decide If Women Can Face POCSO Penetrative Assault
Read More