TARUN KUMAR GHAI Vs MALIBU ESTATE PVT LTD

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION 20 Dec 2007 (2007) 12 NCDRC CK 0012

Judgement Snapshot

Hon'ble Bench

K.S.Gupta , P.D.Shenoy , S.K.Naik J.

Advocates

A.Dwivedi , Malini Sud , N.K.Bansal

Judgement Text

Translate:

1. M/s. Maligo Estate Pvt. Ltd. had floated a scheme by purchasing land in village Tikri, Fatehpur Tehsil, District Gurgaon, Haryana with a view to develop a residential colony to be known as ''malibu Towne'' under the Haryana Development and Regulation of Urban Area Act, 1975 in which residential multi-storeyed housing complex known as ''malibu Condominiums'' was also to be built. Complainant Tarun Kumar Ghai entered into two agreements with the opposite parties and accordingly the complainant was allotted apartment No. 301 in Tower No. 6 having super area 150. 04 sq metres at the rate of Rs. 13,939 per s. m. Total price of flat was estimated at Rs. 22,43,478. First instalment was paid on 17. 2. 1995. The complainant had paid Rs. 21,22,347 to the opposite party leaving balance sum of Rs. 1,20,597 to be paid at the time of possession of flat. As per agreement C-2 the complainant took a second flat in the same tower with apartment No. 503 having super area of 147. 40 s. m. at the same rate with the total price of flat estimated at Rs. 21,23,444. The complainant had already paid Rs. 20,10,392 leaving balance sum of Rs. 1,13,003 to be paid at the time of possession of flat.



2. AS per agreement, the opposite parties were to deliver the apartment to the complainant within three and a half years from the date of booking. As apartment was booked in February, 1995 it was to be given latest by August, 1998. Complainant had visited the site and had come to know that opposite parties have not done any development work and have not constructed any flats on the proposed site. Complainant sent several communications insisting that he should be allotted the flats booked by him. In reply the opposite parties stated that they were offering some other flats in some other tower to the complainant which he had not booked. In this connection complainant pointed that he booked the flats after seeing the sites and had paid a sum of Rs. 80,806 as preferential location charges. Complainant was not interested to swap the flats with any other flats. Complainant has alleged in paras 10 to 13 of his complaint that the acts of the builder amount to deficiency in service and also to be an unfair trade practice falling under Clauses (1) to (5) of 36a of the MRTP Act, 1969, as made applicable to the Consumer Protection Act, 1986 by Section 2 (1) (r) of the said Act.

As the opposite parties did not hand over possession of the booked flats he approached the National Commission with the following prayers:

(a) To direct the opposite parties to hand over the possession of the flats. (b) In case the opposite parties fail to do so, the entire amount paid by the complainant i. e. sum of Rs. 42,13,367 should be refunded back to him along with 18% interest per annum. (c) In view of peculiar facts and circumstances of the case and mental agony and harassment caused by the opposite parties to the complainant special costs and compensation of Rs. 10,00,000 also be given to the complainant in the interest of justice.

This complaint was supported by the affidavit of complainant Tarun Kumar Ghai. Case of the opposite parties



3. THIS was contested by the opposite parties by filing an affidavit in reply. They submitted in the written version that one of the notable factors which had greatly contributed in not picking up the colony is non-existence of infrastructure facilities like schools, hospitals, community centres and other community buildings on the land (sites) set apart for this purpose in the layout plan of the colony. General recession in property market have caused stagnation and in some cases reduction in prices of the properties which in turn has resulted in slow habitation of the colony and non-payment of timely instalments of sale prices by the purchasers of the properties. Opposite party No. 1 had planned and intended to erect multi-storeyed buildings which are to be named as ''malibu Condominiums'' reserved for Group Housing Complex in the layout plan to be given to the intending purchaser on ownership basis. Opposite party No. 1 started construction of 5 tower buildings on the site No. 4 which are almost complete and construction on one building No. 6 was abandoned due to dispute with construction agency. They have not disputed the payment of the same by the complainant for two flats. Opposite party No. 1 had informed the complainant telephonically as well as personally whenever he visited their office that the completion of tower building No. 6 has been delayed due to dispute with construction agency and offered him alternative apartments in other tower buildings, similar in size and all other particulars in lieu of booked apartment in tower building No. 6. Letters were exchanged between the parties on the subject. Instead of conveying his option for alternative apartments the complainant served a legal notice dated 20. 4. 2002 through his Counsel for refund of the amount with 18% interest along with Rs. 10,00,000 as compensation. Legal notice was replied explaining the whole position. They submitted in his written version that a balance of Rs. 4,84,95,986 is due and payable by 217 apartment buyers who have booked the flats in the said tower buildings which are in total 292 apartments. They submitted that these were beyond his control and there was specific clause in the agreement which protected him. Clauses 17 and 19 of the apartment buyers agreement with regard to delivery of the possession of the flat read as under:

"17. That the possession of the said premises is proposed to be delivered by the Company to the Apartment Allottee within three and three and half years from the date of booking of the Apartment. The company shall not incur any liability if it is unable to deliver possession ot the said premises by the time aforementioned, if the completion of the building (s) is delayed by reason of non-availability of steel and/or cement or other building materials, or water supply or electric power or slow down strike or due to a dispute with the construction agency employed by the Company, civil commotion or by reason of war, or enemy action, or earthquake or any Act of God, or if non-delivery of possession is as a result of any act, notice, order, rule or notification of the Government and/or any other public or Competent Authority or for any reason beyond the control of the Company and in any of the aforesaid events the Company shall be entitled to a reasonable extension of time for delivery of possession of the said premises. In the event of any such contingency arising/happening, the Company shall have right to alter or vary the terms and conditions of allotment, or if the circumstances, beyond the control of the Company so warrant, the Company may suspend the Scheme for such period as it may consider expedient and no compensation of any nature whatsoever can be claimed by the Apartment Allottee for the period of suspension of the Scheme. If for the aforesaid or other reasons, the Company is forced to abandon the whole or part of the Scheme, then and in such case, the Company''s liability shall be limited to the refund of the amount paid by the Apartment Allottee without any interest or any other compensation whatsoever.

19. That if for any reason, whether within or outside the control of the Company, the Company is unable or fails to deliver possession of the said premises to the Apartment Allottee within the time specified in Clause No. 17 above, or within any further period or periods as agreed to by and between the parties hereto, then in such case, the Apartment Allottee shall be entitled to give notice to the Company terminating the Agreement in which event the Company shall be at liberty to sell and dispose of the said premises to any person at such price and upon such terms and conditions as the Company may deem fit. The Company shall, within a reasonable time from the date of receipt of such notice and sale of the said premises, refund to the Apartment Allottee the aforesaid amount of earnest money and the further amount that may have been received by the Company from the Apartment Allottee as part payment (s) in respect of the said premises. Neither party shall have any other claim against the other in respect of the said premises or arising out of this Agreement. "

Some apartment allottees of tower building No. 6 have in their wisdom accepted alternate apartment floor in building No. 5 or in personal floor scheme which option was not exercised by the complainant. It is specifically denied that case explained in paras 10 to 13 of the complaint amounts to deficiency in service and also amounts to unfair trade practice. Opposite parties requested that the complaint is liable to be dismissed with cost. Interim orders of National Commission and High Court of Delhi



4. WHEN the matter was being heard by this Commission on 2. 3. 2005 the learned Counsel for the opposite parties stated that an amount of Rs. 41,32,000 deposited by the complainant would be paid within four weeks. The Commission ordered thus: "this payment is without prejudice to the rights of the parties to agitate the question of interest payable on the said amount by the opposite parties".

When the matter came up for hearing on 5. 10. 2005, the Commission observed as follows: ''heard the proxy Counsel for the opposite party and the complainant in person. Admittedly, opposite party has refunded the amount of Rs. 41,33,137 by cheque dated 28. 3. 2005. It is pointed out that the said amount was paid by the complainant to the opposite party in February 1995. It is also pointed out that construction of the Block for which the complainant has booked flats, is abandoned for one reason or the other, and the complainant had not accepted the alternative offer of the flats made by the opposite party. That offer was made only in March/july 2001. The complainant, who is appearing in person, pointed out that there was an tripartite agreement between the complainant, the opposite party and the CITI Bank with regard to the loan amount taken by the complainant for the CITI Bank. That amount was taken by paying interest at the rate of 17% per annum. Considering this aspect, for the time-being, and without prejudice to the rights of the complainant and the opposite party, we direct the opposite party to pay interest at the rate of 10% per annum from 1. 8. 1995 till 1. 5. 2005 within a period of four weeks from today. "

The opposite party challenged the order dated 5. 10. 2005 by filing writ petition before the Delhi High Court. By the order dated 28. 4. 2006, the writ petition was disposed of with direction that the amount covered by said date 5. 10. 2005 be deposited before this Commission within four weeks and same be invested in FDR and this deposit shall be subject to final decision in the complaint. The cheque of Rs. 36,08,435 covering interest upto 1. 5. 2005 was deposited by the opposite party with this Commission on 24. 5. 2006. This amount was directed to be invested by the Registry in fixed deposit immediately.



5. THE aforesaid order was passed on 26. 4. 2007. The above interim orders indicate that the dispute falls in a narrow compass and it pertains only to the liability of the builder to pay interest. Two issues which are important- (1) whether any interest is to be paid? and (2) if so, at what rate? submission of the learned Counsel for the complainant



6. HE read the prayer clause of the complaint wherein he has pleaded that complainant had demanded 18% interest on the amount paid along with Rs. 10,00,000 as compensation. He submitted that he had borrowed loan @ 17% from the Citi Bank under a tripartite agreement hence the opposite party is liable to pay him atleast 17% interest. The builder had not built the flats for three and a half years, so he was keen to get the refund of the amount. He was not interested in alternate flats because he was keen on the flots booked due to preferential location etc. Submission of the learned Counsel for the opposite party

Due to dispute between the builder and the contractor he could not complete the flats booked by the complainant. Accordingly, he offered identical flats in tower B which was refused by the complainant. He quoted a clause of the agreement wherein it is stated (quoted supra) "if for the aforesaid or other reasons, the Company is forced to abandon the whole or part of the Scheme, then and in such case, the Company''s liability shall be limited to the refund of the amount paid by the Apartment Allottee without any interest or any other compensation whatsoever". Accordingly he is not liable to pay any interest. He further submitted that as per the judgment of the Supreme Court in Ghazibad Development Authority v. Balbir Singh 10% interest is reasonable. He also pointed out that the complainant had repaid the loan taken from Citi Bank on 14. 10. 1998 with 17% interest and after that he did not have any liability. He also pointed out the case of Bangalore Development Authority v. Syndicate Bank, II (2007) CPJ 17 (SC)=i (2008) SLT 761= (2007) 6 SCC 711, wherein it is held that "where an alternative site is offered or delivered (at the agreed price) in view of its inability to deliver the earlier allotted plot/flat/house, or where the delay in delivering possession of the allotted plot/flat/house is for justifiable reasons, ordinarily the allottee will not be entitled to any interest of compensation. This is because the buyer has the benefit of appreciation in value". "the quantum of compensation to be awarded, if it is to be awarded, will depend on the facts of each case, nature of harassment, the period of harassment and the nature of arbitrary or capricious or negligent action of the authority which led to such harassment". Findings:

It is not in dispute that for allotment of apartment No. 301 in Tower No. 6 the complainant had paid Rs. 21,22,347 to the builder leaving a balance of small sum of Rs. 1,20,597. Similarly, as per agreement No. C-2 in the same tower for apartment No. 503 the complainant had paid Rs. 20,10,392 leaving a balance of Rs. 1,13,003 to be paid at the time of possession of the flat. As the apartments were booked in February, 1995 possession of the built apartment should have been given at least by August, 1998. Despite several visits and correspondence with the builder the booked flats were not given. On the other hand builder insisted that they should swap the flats with other flats in other towers which was not agreed to by the complainant as he had paid Rs. 80,806 as preferential location charges. Accordingly, the complainant filed a complaint before this Commission praying for direction to the opposite party to handover possession of the flats and in the alternative to refund Rs. 42,13,367 along with 18% interest per annum with Rs. 10,00,000 special cost and compensation.



7. THE respondent gave several reasons for non-completion of the flats like non-existence of infrastructural facilities; several other allottees of flat had not paid the amount and dispute with construction agency etc. Though the first instalment was paid way back on 17. 2. 1995 and subseguent instalments shortly thereafter, for 10 years the builder did not refund a single paise. On 2. 3. 2005 this Commission directed the opposite party to refund Rs. 41,32,000 within four weeks without prejudice to the rights of the parties to agitate the question of interest payable on the said amount by the opposite parties. On 5. 10. 2005 when the case came up for hearing complainant submitted that he had taken a loan from Citi Bank by paying interest @ 17% per annum. Considering this aspect and observing that as the builder had abandoned the construction of booked flats for one reason or the other and made an offer for an alternate flat only in March/july 2001 this Commission ordered that without prejudice to either parties, the opposite party was directed to pay interest @ 10% per annum from 1. 8. 1995 till 1. 5. 2005 within a period of four weeks. This was challenged by filing Writ Petition before the Delhi High Court which disposed of the petition with direction to deposit the amount with this Commission which to be invested in FDR and this deposit shall be subject to final decision in the complaint. Accordingly, the amount of Rs. 36,08,435 was deposited in this Commission on 24. 5. 2006 to be invested by the Registry in FD.

It is not disputed that first instalment was paid as long back as on 17. 2. 1995 and subsequent instalments were paid shortly thereafter. It is also not in dispute for more than a decade the builder did not refund any amount to the consumer, which means that builder has utilised this money, which would naturally carry interest as an opportune cost. So the builder cannot be absolved of the responsibility to pay interest to the purchaser. Accordingly, the first issue is answered in the positive i. e. the builder is liable to pay interest.



8. THE second issue to be answered is rate of interest payable as the principal amount has already been paid to the complainant. Complainant has demanded @ 18% interest along with Rs. 10,00,000 as compensation. There is a tripartite agreement between Malibu Estates-the builder, Tarun Ghai-complainant and the Citi Bank signed by all the parties of the year 1995 which clearly mentions that the complainant borrowed Rs. 14,77,000 which carried interest @ 17%. Clause 17 page-17 of the agreement signed between the builder and the complainant says if for certain reasons, the Company is forced to abandon the whole or part of the Scheme, then and in such a case, the Company''s liability shall be limited to the refund of the amount paid by the apartment allottee without any interest or any other compensation whatsoever. As against this, there is another clause in the agreement wherein it is stipulated in the event of default which is as follows:

"10. That without prejudice to the Company''s rights under this Agreement and/or law the Apartments Allottee shall be liable to pay to the Company interest at the rate of 20% per annum on all amounts due and payable by the Apartment Allottee under this Agreement for the period of delay in making such payments. This discretion for termination of the agreement or acceptance of the delayed payment with interest at the rate of 20% per annum shall exclusively vest with the Company. In the event of the Company waiving its right to cancel the allotment and forfeit the earnest money and accepting payment with interest in its place, no right whatsoever would accrue to any other defaulting Apartment Allottee on that account. "

As per this agreement if the builder abandons whole or part of the scheme the builder''s liability is only limited to the refund of the amount paid by the apartment allottee without any interest or compensation whatsoever. On the other hand, if there is any delay in making payments of the instalments by the apartment allottee he is liable to pay 20% interest on all amounts due. Hence, this agreement is inequitable.

The builder has withheld re-payment of money deposited by the complainant for 10 long years and enjoyed the usufructs of this deposit. So, he cannot compel the allottees to pay 20% interest if there was default or delay on their part and at the same time not pay any interest to the allottees when he had illegally withheld their money without giving them the flat booked despite written agreements. He is aware of the fact that the complainant had borrowed money to partly finance these two flats from the Citi Bank @ 17% interest.



9. IN this connection, it is worthwhile to go through the judgment of Hon''ble Apex Court in Ghaziabad Development Authority v. Balbir Singh, II (2004) CPJ 12 (SC)=iii (2004) SLT 161= (2004) 5 SCC 65 as follows:

"8. However, the power and duty to award compensation does not mean that irrespective of facts of the case compensation can be awarded in all matters at a uniform rate of 18% per annum. As seen above, what is being awarded is compensation i. e. a recompense for the loss or injury. It therefore necessarily has to be based on a finding of loss or injury and has to correlate with the amount of loss or injury. Thus the Forum or the Commission must determine that there has been deficiency in service and/or misfeasance in public office which has resulted in loss or injury. No hard and fast rule can be laid down, however, a few examples would be where an allotment is made, price is received/paid but possession is not given within the period set out in the brochure. The Commission/forum would then need to determine the loss. Loss could be determined on basis of loss of rent which could have been earned if possession was given and the premises let out or if the consumer has/had to stay in rented premises then on basis of rent actually paid by him. Along with recompensing the loss the Commission/forum may also compensate for harassment/injury, both mental and physical. Similarly, compensation can be given if after allotment is made there has been cancellation of scheme without any justifiable cause.

9. That compensation cannot be uniform and can best be illustrated by considering cases where possession is being directed to be delivered and cases where only monies are directed to be returned. In cases where possession is being directed to be delivered the compensation for harassment will necessarily have to be less because in a way that party is being compensated by increase in the value of the property he is getting. But in cases where monies are being simply returned then the party is suffering a loss inasmuch as he had deposited the money in the hope of getting a flat/plot. He is being deprived of that flat/plot. He has been deprived of the benefit of escalation of the price of that flat/plot. Therefore the compensation in such cases would necessarily have to be higher. Further if the construction is not of good quality or not complete, the compensation would be the cost of putting it in good shape or completing it along with some compensation for harassment. Similarly, if at the time of giving possession a higher price or other amounts are collected unjustifiably and without there being any provision for the same the direction would be to refund it with a reasonable rate of interest. If possession is refused or not given because the consumer has refused to pay the amount, then on the finding that the demand was unjustified the consumer can be compensated for harassment and a direction to deliver possession can be given. If a party who has paid the amount is told by the authority that they are not in a position to ascertain whether he has paid the amount and that party is made to run from pillar to post in order to show that he has paid the amount, there would be deficiency of service for which compensation for harassment must be awarded depending on the extent of harassment. Similarly, if after delivery of possession, the sale deeds or title deeds are not executed without any justifiable reasons, the compensation would depend on the amount of harassment suffered. We clarify that the above are mere examples. They are not exhaustive. The above shows that compensation cannot be the same in all cases irrespective of the types of loss or injury suffered by the consumer. "



10. THE case quoted by the respondent i. e. Bangalore Development Authority (BDA) v. Syndicate Bank (supra), is distinguishable from the case on hand. The BDA does not construct buildings and offers flats to the buyers. BDA develops land and allot plots. BDA is a public authority constituted under the statue with the no profit motive and even at the time of allotment of a plot the price of the plot/land is generally offered less than the market price. The allottees get high appreciation and value in subsequent years for the plots which they get from the BDA and the case relates to such allotment where delay was there for justifiable reasons. In the case on hands, the respondent wanted to develop residential complex with the profit motive and there was no justifiable reason for delay in allotting it. In fact they did not allot the booked flat at all which was in preferential locality for which higher price was obtained. On the other hand they offered, alternative flats in other sites/ towers which was not booked by the complainant. Further they unjustifiably withheld the amount paid by the complainant. The principal amount was paid to the complainant only after several years of deposit in pursuance of the orders passed by this Commission. Hence, respondent cannot get support from the case quoted (supra) by them.

Accordingly, it is absolutely clear that the compensation varies from case to case depending upon the facts and circumstances of the case. No uniform rates can be fixed. Compensation cannot be same in all cases irrespective of the type of loss or injury suffered by the same. The complainant has claimed only 18% interest hence we will not apply the rate of interest which is mentioned in the bipartite agreement for the defaulters i. e. @ 20%. Considering the fact that flat was not handed over for 10 long years and only alternate flats in an alternate building which was located in a less preferential area was offered which was not acceptable to the complainant and the money deposited was illegally withheld by the builder enjoying the usufructs of that and also looking into the fact that 17% was the rate of interest charged by the Citi Bank for the loan obtained by the complainant/borrower with the knowledge of the builder as it was a tripartite agreement, we deem it fit to award 17% interest from the date of deposit till the date of payment.

Amount deposited as per our order i. e. Rs. 36,08,435 along with the accrued interest is directed to be released in favour of the complainant in the meantime. Balance amount of interest will be paid within six weeks by the opposite parties to the complainant. In the facts and circumstances of case, we deem it fit to award a cost of Rs. 30,000. Complaint is disposed of in above terms. Complaint disposed of.

From The Blog
Madras High Court to Hear School’s Plea Against State Objection to RSS Camp on Campus
Feb
07
2026

Court News

Madras High Court to Hear School’s Plea Against State Objection to RSS Camp on Campus
Read More
Delhi High Court Quashes Ban on Medical Students’ Inter-College Migration, Calls Rule Arbitrary
Feb
07
2026

Court News

Delhi High Court Quashes Ban on Medical Students’ Inter-College Migration, Calls Rule Arbitrary
Read More