P.C. Sharma and Co. Vs Delhi Development Authority

Case No: CS (OS) 2057A of 1996

Date of Decision: July 2, 2010

Acts Referred: Arbitration Act, 1940 — Section 20, 29, 30, 33

Hon'ble Judges: Rajiv Sahai Endlaw, J

Bench: Single Bench

Advocate: Sandeep Sharma and Vikas Sharma, for the Appellant; Bhupesh Narula, for the Respondent

Translate: English | हिन्दी | தமிழ் | తెలుగు | ಕನ್ನಡ | मराठी

Judgement

Rajiv Sahai Endlaw, J.@mdashThe objections (IA No. 12005/1996) preferred by the respondent Delhi Development Authority (DDA) u/s 30 &

33 of the Arbitration Act, 1940 upon being served with the notice of the filing of the award dated 30th April, 1996 in this Court are for

consideration. The petitioner P.C. Sharma & Company has not preferred any objections to the award.

2. The disputes arose between the parties out of the contract dated 14th September, 1982 awarded by the respondent DDA to the petitioner

contractor for construction of 540 houses under the Self Financing Scheme. The estimated cost put to tender of the said works was of Rs.

2,37,98,571/- and the work was to start on 24th September, 1982 and to be completed by 23rd September, 1983. The works were however

completed on 31st January, 1986. On the arbitration clause being invoked by the petitioner contractor, the respondent DDA appointed Shri G.S.

Rao, retired Director General (Works) as the Arbitrator. The Petitioner contractor made claims under as many as 34 heads and for a total sum of

Rs. 1,07,65,314/- along with interest and costs against the respondent DDA. The Arbitrator has allowed claims for a total sum of Rs. 35,75,931/-

and has also awarded interest thereon, pendente lite at the rate of 15% per annum and future at the rate of 18% per annum.

3. The counsel for the petitioner contractor at the outset has contended that the scope of interference by this Court in the award is limited. Reliance

in this regard is placed on:

(i) Judgment dated 17th December, 1999 of this Court in Suit No. 21-A/1996 titled Sh. Anil Garg v. DDA. However, the same is a judgment on

the requirement of giving reasons and that the Arbitrator is only required to indicate the trend of his thought process but not his mental

meanderings. It was also reiterated that the reasonableness of the reasons given by the Arbitrator cannot be challenged and that if on a reading of

the award it is obvious that the Arbitrator at the time of the passing of the award has dealt with the rival contentions in perspective, then the award

sufficiently complies with the requirement of giving reasons.

(ii) Judgment dated 19th March, 2009 of the Division Bench of this Court in FA(OS) No. 267/1996 titled DDA v. Madhur Krishna. This

judgment is again on the same aspect as in Anil Garg (supra).

(iii) Delhi Development Authority Vs. Bhagat Construction Co. (P) Ltd. and Another, where the Division Bench of this Court held that where the

Arbitrator is a retired Chief Engineer of CPWD and thus well conversant with the kind of disputes he is adjudicating, the Court ought not to

substitute its own view on the opinion taken and the decision rendered by the Arbitrator unless and until the decision of the Arbitrator is manifestly

perverse or has been arrived at on the basis of wrong application of law.

(iv) D.D.A. Vs. Bhagat Construction Co. Pvt. Ltd., where also the Division Bench of this Court for the reason of the Arbitrator, being well versed

in the matter being the former Director General of CPWD, held no interference possible in the award.

(v) Arosan Enterprises Ltd. v. Union of India 1999 (3) Arb. LR 310 (SC) holding that the interference by the Court u/s 30 is rather restrictive and

the Arbitrator being the judge chosen by the parties, his decision is final and reappraisal of evidence, and interference where two views are

possible is not permissible and the Court cannot substitute its evaluation for that of the Arbitrator except in the case of patently erroneous findings,

easily demonstrable from the material on record.

(v) Sudarsan Trading Co. Vs. Government of Kerala and Another, holding that interpretation of contract is a matter for the Arbitrator on which

Court cannot substitute its own decision and carving out a distinction between disputes as to the jurisdiction of the Arbitrator and the disputes as to

in what way that jurisdiction should be exercised.

(vi) Order dated 2nd February, 2009 of the Division Bench of this Court in FA(OS) No. 143/2006 titled DDA v. P.C. Sharma & Co. negating

the objection as to the claims allowed being overlapping and holding the claims for prolongation of contract, for site expenses and for loss of

profitability to be forming three distinct heads of damages.

(vii) Goa, Daman and Diu Housing Board Vs. Ramakant V.P. Darvotkar, ; however the said judgment is not found apposite to the matter in

controversy.

4. The objections of respondent DDA are hereafter taken up claim wise.

Re: Claim No. 1

5. This claim was for refund of Rs. 1,32,460/- deducted by the respondent DDA out of payment made to the petitioner contractor towards rebate

for timely payments of bills. The Arbitrator has allowed the claim to the extent of Rs. 35,380/-. Under the contract the respondent DDA was

entitled to rebate of 0.5% for making monthly payments of the running bills. It was the admitted position that neither monthly running bills were

submitted nor were payments made monthly. It was the case of the respondent DDA that the responsibility for preparing and submitting the bills

was of the petitioner contractor and the petitioner contractor having not prepared and submitted monthly bills, it could not make the monthly

payments but the same would not deprive it of the benefit of the rebate. It was the case of the petitioner contractor that no date was fixed for the

petitioner contractor to submit the monthly bills and in any case as per the practice of the respondent DDA, it was the Executive Engineer of DDA

who was to get the bills prepared after getting the measurement of the work done. The Arbitrator found that in May, 1983 no running bill was

paid; in August, 1985, though two bills were paid but because respondent DDA did not have enough funds to honour these two bills, an amount of

Rs. 60,000/- was withheld; again in October, 1985, the respondent DDA did not have funds and hence an amount of Rs. 1,50,000/- was

deducted which was paid along with bill of November, 1983. Accordingly, the claim to the extent of Rs. 35,380/- only was allowed.

6. The counsel for the respondent DDA has contended that the Arbitrator has without any basis believed the contention of the petitioner contractor

of the practice prevalent in DDA; it is further contended that in any case the contractor first has to submit the bills for measurement and without the

contractor taking the first step, the respondent DDA itself cannot prepare the bills. It is also urged that there was nothing before the Arbitrator to

show that there was any fund problem with the respondent DDA, a chart is handed over to show that payments were made every month.

7. Per contra the counsel for the petitioner contractor in this regard relied on Sanyukt Nirmata Vs. Delhi Development Authority and Another,

where this Court held that the pre-requisite for submission of the bills is the date to be fixed by the Engineer In-Charge. It is contended that without

any date being fixed in the present case also for submission of the bills, no delay can be attributed to the petitioner contractor. Attention is also

invited to the second hearing before the Arbitrator held on 9th April, 1990 where the Executive Engineer of the DDA had admitted the correctness

of the statement of payments by the petitioner contractor and wherein short payment forming the basis of the award under this claim is reflected.

8. In the absence of the respondent DDA being able to demonstrate that a date was fixed for the petitioner contractor to raise the bill, the

judgment in Sanyukt Nirmata (supra) would apply. Moreover the findings as to whether the payments were made so as to entitle the respondent

DDA to rebate or not is a finding of fact and if this Court were to interfere with such findings, no distinction will be left between an appeal and in a

challenge to the award. The objection to award under Claim No. 1 is thus dismissed.

Re: Claim No. 3

9. This claim was of Rs. 1,77,945/- for cost of cement slurry used in roughcast plaster. It was the case of the petitioner contractor that the

application of cement slurry was necessary to secure proper bond for roughcast plaster and was directed to be done by the Executive Engineer

and the costs thereof were included in the analysis sent by the Executive Engineer to the Superintending Engineer but sanction thereof was not

obtained. The respondent DDA did not dispute the application of cement slurry but contends that it was not provided for and the cost of ordinary

plaster only was provided for in the schedule of rates. The Arbitrator, assuming the costs of extra labour as 50 paise per sq.mt. awarded a sum of

Rs. 31,890/-.

10. The counsel for the respondent DDA has contended that the award is on the basis of assumption without reference to any actual data; that

even if assumptions were to be made, the same ought to have been made on the basis of CPWD rates or DSR rates and there is no basis for the

assumption made in the award. The counsel for the petitioner contractor on the other hand contended that such assumption is on the basis of the

experience of the Arbitrator. Reliance is placed on Delhi Development Authority Vs. Polo Singh and Co., where a Division Bench of this Court

reiterated that interference with award even if based on guess work is not permissible.

11. In view of it being undisputed that the cement slurry was used and the rate thereof not provided for, no case for interference with the award is

made out inasmuch as the reasoning given by the Arbitrator is a possible reasoning and this Court cannot substitute its view for the same.

Re: Claim No. 5

12. The petitioner contractor claimed Rs. 5,572/- towards extra labour for filling concrete in door frames and consolidating the same; it was its

case that the rate at which the said claim was made, was accepted by the respondent DDA by paying / sanctioning the running bills at the said rate

but was subsequently declined. It was the contention of the respondent DDA that payment under the running bills, as per the terms of agreement, is

merely by advance and payment under the running bills at the increased rate was not binding in any manner on the respondent DDA. The parties

were also at issue as to whether any extra labour at all was involved in filling concrete in the door frames. The Arbitrator concluded that compared

to mass concrete the work involved in filling concrete in small sections of pressed steel is more involved and extra labour is involved and hence

allowed the claim.

13. The counsel for the respondent DDA has contended that there was no proof of any extra work being involved and in the absence thereof the

same ought not to have been allowed. It is also contended that the said work was admittedly part of the contract and no rate having been provided

therefore in the contract, could not be claimed or awarded. Per contra the counsel for the petitioner contractor has contended that the Arbitrator

has applied his expert knowledge in concluding that extra work/labour is involved in filling concrete on door frames and the same ought not to be

interfered with. He has also taken me through the claim before the Arbitrator and the reply thereto to demonstrate that the only question for

adjudication before the Adjudicator was of the rate to be applied to the said work and there was no controversy before the Arbitrator that a

separate rate for the said work had to be applied for and the only question was of the rate to be applied.

14. I find that the contention of the petitioner contractor and the pleadings before the Arbitrator show that the only controversy with respect to the

said claim was as to the rate to be applied for the work of filling concrete on door frames. For the reason of the respondent DDA having not

objected to the rate in the running bills and for the reason of the Arbitrator, who was admittedly an expert, having applied his experience and

expertise in concluding the rate to be applied, no interference in the award under the said claim is called for and the objections to the award under

the said claim are also dismissed.

Re: Claim No. 8

15. Claim No. 8 for Rs. 6,07,726/- was on account of extra work/effort required to be undertaken by the petitioner contractor for the reason of

the respondent DDA having changed the layout plan. The respondent DDA controverted that the layout plan had been changed. The award

however records that the respondent DDA in its written arguments admitted some charge in the orientation of blocks. The Arbitrator found a

change in plans and that the new site was hilly and undulating resulting in slow progress of work and that the change involved shifting of the labour

camp also. The Arbitrator held the claim to be ""more or less correct"" but being not convinced of the amount claimed under the said claim, awarded

only Rs. 1,00,000/-.

16. The counsel for the respondent DDA has contended that the Arbitrator has not even returned a definite finding of the claim being correct and

has arbitrarily awarded Rs. 1,00,000/-. It is also urged that the denial by the respondent DDA of any change in plans has not been considered.

Attention in this regard is also invited to Annexure R-3 in the Arbitrator''s record and to the drawing register and it is contended that there was no

change in plan. Per contra the counsel for the petitioner contractor contends that the finding being factual cannot be interfered with. Reliance is

placed on Bhagat Construction Co. (P) Ltd. (supra) where owing to the experience and expertise of the Arbitrator, the Court had refrained from

interfering with the award.

17. There is no challenge to the finding of the Arbitrator of the respondent DDA in the written arguments having admitted to the change in

orientation of blocks. It is not as if the Arbitrator has allowed the entire claim of the petitioner contractor. Less than 1/6 of the claimed amount has

been awarded. In view of the admission of some change, the assessment of the Arbitrator of the extra work involved therefore cannot be interfered

with. The respondent DDA had the choice to appoint an Arbitrator and appointed a technical person rather than a legal person. The sole purpose

of appointment of a technical rather than a legal person as an Arbitrator is to take benefit of the special knowledge of the Arbitrator relating to the

matters in dispute. Once a change in plan is admitted, the reasoning of the Arbitrator of the new site requiring additional labour is a finding of fact

and the assessment by the Arbitrator of the value of the extra work entailed is not interferable. After all, all such matters cannot be measured with

precision. There is a certain amount of estimation to be made. It is for such estimation only that a technical person was chosen as the Arbitrator. As

for the language used by the Arbitrator, he is not a person steeped in law. The language used by the Arbitrator of the claim being ""more or less

correct"" cannot be read to mean that the Arbitrator was unsure of the basis of the claim. The Arbitrator has used the expression ""more or less"" only

for the reason of the change being not of the magnitude as claimed by the petitioner contractor but of a lesser magnitude. The objection to the

award under the said claim is thus also dismissed.

Re: Claim No. 9

18. The petitioner contractor had claimed Rs. 2,64,920/- by way of refund of the rebate for charges for water not supplied by the respondent

DDA. As per the agreement, it was to be supplied by the respondent DDA at a single point at site and further distribution was the responsibility of

the petitioner contractor. The Arbitrator found and it is not disputed, that arranging of an electricity connection for drawing the water at the said

point was the responsibility of the respondent DDA. It was the admitted position that though the respondent DDA applied for electricity

connection for operating the pump for drawing the water but the same was not obtained till the completion of the work and for which reason the

petitioner contractor supplied electricity for the said pump from its own connection. Though a sub meter was installed to measure the electricity

consumption for operating the pump but the same was done after sometime; the claim was of the electricity consumption for the said pump before

the installation of the sub meter and for water obtained from tankers when the pump failed to function for non maintenance thereof by the

respondent DDA. There is no dispute about the said factual position. The Arbitrator, finding that the petitioner contractor had borne electricity

charges for the pump for the initial period, awarded Rs. 50,000/- against the said claim.

19. The contention of the respondent DDA is that the said amount awarded under the claim is without any quantification and evidence. On inquiry

as to what evidence could have been led by the petitioner contractor, the counsel for the respondent DDA states that use of diesel for operating

the generator for running the said pump could have been shown.

20. In view of it being not disputed that the petitioner contractor did for sometime bear electricity charges which the respondent DDA was to bear,

no interference with the award, even if on estimation basis, is called for and the award is not found to be perverse. The respondent DDA has been

unable to show as to what the award for the amount admittedly due should have been, if not Rs. 50,000/. Again for such claims there is bound to

be an element of estimation and guess work and without it being shown that the estimation based on the guess work is perverse, the Court can

neither substitute any other amount nor is it in the fitness after a long lapse of time to remand the matter. The objections to award under Claim No.

9 are also dismissed.

Re: Claim No. 10

21. The said claim was for Rs. 27,521/- for use of white cement for affixing the tiles. Under the contract, the cement was to be supplied by the

respondent DDA. It was the case of the petitioner contractor that the respondent DDA supplied grey cement only and which if it had been used

for affixing the glazed tiles would have affected the colour of the tiles and that white cement is normally used for affixing the tiles. The petitioner

contractor, therefore, used white cement and made the claim for the difference in cost of grey cement and the white cement. The Arbitrator found

that the use of white cement was not disputed. It was the case of the respondent DDA that under the contract the petitioner contractor was not

entitled to the extra cost of white cement. The Arbitrator found that the respondent DDA has not contested the quantity of white cement used by

the petitioner contractor or the rate thereof and accordingly allowed the claim in toto.

22. The counsel for the respondent DDA contends that the use of white cement in affixing the tiles is not as per the contract or as per the CPWD

specifications. Per contra the counsel for the petitioner contractor relies on Villayati Ram Mittal Vs. Union of India and Others, , copy whereof

was filed as C-1 13 before the Arbitrator also in this regard. Even though in the present case it was not provided in the contract that the glazed tiles

were to be affixed by white cement, as in the Villayati Ram Mittal (supra) but it cannot be denied that if the glazed tiles had not been affixed with

white cement and had been affixed with grey cement, they would have lost their colour and the use of white cement being for the benefit of the

respondent DDA and in accordance with the standard practices, the award under this claim cannot be interfered with and the objection is

dismissed.

Re: Claim No. 11

23. This claim of Rs. 5,81,890/- for straightening and cutting of steel bars was allowed to the extent of Rs. 1,14,400/-. The law with respect to the

said claim is no longer res-integra. In Wee Arr Construction Builders v. DDA 2001 (IV) AD (Delhi) 65 as reiterated in Anant Raj Agencies v.

DDA 2005 (1) Arb. LR 590 this Court has held that bending, binding and placing in position steel for RCC work is included in the contract and

the said work necessarily requires the process of straightening of steel before cutting and it was held that no claim for extra was maintainable on

such account. It was also held that the contractor cannot make such a claim for the reason of having not given any notice to the respondent DDA

at the time of carrying out the said work that the same was to be treated as an additional/extra work. The counsel for the petitioner contractor

admitted the said legal position and stated that he will check up and inform whether there was any evidence in the present case of such notice

having been given. However, the counsel for the petitioner contractor has not shown any evidence of such notice having been given.

24. The award does not record that any such notice was given. Resultantly the objection to the award of Rs. 1,14,400/- under the said claim is

allowed and the award under the said claim is set aside.

Re: Claim No. 12

25. The petitioner contractor claimed Rs. 1,38,724/- in respect of overweight of steel. Under the agreement, steel was to be issued by the

respondent DDA. While measure of steel at the time of issuance was by actual weight, the consumption thereof by the petitioner contractor was by

other measure. The Arbitrator allowed the said claim to the extent of Rs. 98,750/- by calculating overweight as the rate of 4% for 8mm and 3%

for 10mm to 12mm steel.

26. The counsel for the respondent DDA has challenged the said award as presumptive and has contended that Clause 42 of the contract

provided for unutilized steel and shows there was no question of overweight. It is further contended that the petitioner contractor did not return any

steel and hence no case for allowing claim on account of overweight was made out. Per contra the counsel for the petitioner contractor has

contended that the recovery on account of steel was being made by the respondent DDA from the petitioner contractor in excess of the quantity

given and hence the need for applying overweight arose.

27. The Arbitrator has also recorded that the petitioner contractor has not returned any steel. Nevertheless, claim on account of overweight has

been allowed because though the quantity of steel measured at the time of issuance was 536.875 MT, recovery on account of cost of steel was

being made for 581.8502 MT. The said figures have not been disputed by the counsel for the respondent DDA. If the respondent DDA had

issued 536.875 MT of steel, it could have made recovery for that quantity only and not for any excess quantity. The respondent DDA itself having

claimed price of excess quantity then issued, cannot object to the formula of overweight being applied by the Arbitrator. The contention of the

respondent DDA was that the said formula has to be as per Clause 42 only. The Arbitrator has however held that Clause 42 does not require

diameter wise tallying. It was the contention of the petitioner contractor that the field staff of the respondent DDA maintained the register of

overweight and on which its signatures were taken but the said register was not produced by the respondent DDA. It was in these circumstances

that the Arbitrator, not accepting the claim of petitioner contractor of overweight at the rate of 5% in overall diameter, allowed the claim only to the

extent of Rs. 98,750/-.

28. I do not find the view of the Arbitrator in the circumstances to be an impossible one. Once it is a possible view, the same does not call for any

interference and the objections are dismissed.

Re: Claim No. 18

29. The petitioner contractor claimed Rs. 40,70,423/- in respect of payment for work done beyond stipulated date of completion. The respondent

DDA had extended the time for completion without taking any action for delay against the petitioner contractor. The Arbitrator therefrom

concluded that the respondent DDA admitted delay to be on its own account. The petitioner contractor made a claim for increase in costs during

the period of said extension. The respondent DDA contested that the petitioner contractor at the time of extension had given in writing that it will

not make any claim on account of delay. The petitioner contractor contended that it was forced to give such writing as otherwise the respondent

DDA would not have given extension and claimed that the construction costs has been increasing at the rate of Rs. 2.24% per month. The award

records that the respondent DDA had not challenged the said figure. The Arbitrator finding that the bulk of the work was completed by June, 1984

when some allottees had started taking possession, computed the additional costs incurred by petitioner contractor on account of delay to be of

Rs. 24,00,000/- and allowed the same. The Arbitrator while so computing took the value of the work done in the period of delay to be of the

value of Rs. 200 lakhs.

30. The counsel for the respondent DDA has contended that even if the work done during the period of delay was of the value of Rs. 200 lakhs,

the said value of Rs. 200 lakhs included the costs of material i.e. cement and steel etc. supplied by the respondent DDA and thus the computation

of Rs. 200 lakhs on this basis is inherently defective. It is further contended that the total value of the work was of Rs. 263 lakhs and in the said

total value the materials supplied by the respondent DDA was of Rs. 82 lakhs; so even if the work done during the period of delay was of Rs. 200

lakhs, it would still include the value of materials supplied by the respondent DDA and with respect whereto no increase could be awarded.

31. It is also contended by counsel for the respondent DDA that the said award is without any basis. There was no evidence for the Arbitrator to

conclude the value of the work done during the period of delay as Rs. 200 lakhs; no records were kept or shown in this regard.

32. It is also contended that not demanding compensation while granting extension could not have been deemed to be an admission by the

respondent DDA of the delay being on its own account.

33. It is further contended that the plea of having been forced to give an undertaking not to claim any amount on account of extension of time for

completion of work was taken by the petitioner contractor only for making the claim and after three years from giving the said certificate and not at

the contemporaneous time. It is urged that in the circumstances, the Arbitrator could not have concluded that the respondent DDA has forced the

petitioner contractor to give such no claim certificate.

34. It is further the contention of the counsel for the respondent DDA that under Clause 1 0C of the agreement, increase in price of material and

labour was reimbursable if such increase is caused by Government and only on the contractor furnishing proof of having incurred the extra

expenditure. It is contended that the claim, if any, of the petitioner contractor could have been under Clause 1 0C only and not otherwise as

allowed by the Arbitrator; in the absence of any proof of extra expenditure having been furnished, claim on account of delay could not have been

allowed on the formula of general increase in costs of construction.

35. Reliance in this regard is placed on:

(i) Steel Authority of India Limited Vs. J.C. Budharaja, Government and Mining Contractor, laying down that award of damages ignoring a

prohibition in the contract in that respect is without jurisdiction.

(ii) Kochar Construction Co. v. Union of India 1994 (1) Arb. LR 269 where the Division Bench of this Court held that mere filing of costs analysis

cannot be accepted as evidence of expenditure on account of increased costs of construction even if costs analysis is not disputed/controverted.

(iii) Anant Raj Agencies (supra) where this Court held that where contract provides for a formula as per which escalation has to be worked out,

the Arbitrator is bound by the contract and cannot adopt a different methodology.

(iv) Judgment dated 13th July, 2009 in CS(OS) No. 154/1994 titled Republic Construction Co. v. DDA and judgment dated 23rd July, 2009 in

CS (OS) No. 4405A/1992 titled Verma Construction Co. v. DDA where this Court has held that a claim under Clause 10C lies only if during the

progress of work, price of any material (not being a material supplied from the Engineer-In-Charge store) or wages of labour increases because of

coming into force of any fresh law, statutory rule or order and such increase exceeds 10% of the prices/wages prevailing at the time of the receipt

of tender; the contractor can claim reimbursement of prices only if it is more than 10% and only to the extent it was in excess of 10% and if he

serves a notice on DDA during progress of work. Such reimbursement on increase of prices/labour is to be made only if it is approved by the

Superintending Engineer. It was further held that an enhancement under Clause 1 0C can be allowed only if the conditions as set out therein are

satisfied and no presumption could be drawn by the Arbitrator that because of the contract over-running, there was necessarily going to be a price

rise and necessarily going to be a wage rise. The award on such basis was held to be contrary to the contract and was set aside.

36. Per contra the counsel for the petitioner contractor has contended that had the petitioner contractor not given the no claim undertaking on

account of delay, the respondent DDA would not have granted the extension. It was enquired from the counsel for the petitioner contractor

whether the contractor had contemporaneously written any letter that it has been so forced to give the no claim undertaking. Though no letter was

shown but the counsel for the petitioner contractor contended that since the arbitration had already been invoked and the petition u/s 20 had been

filed, the occasion for writing such a letter did not arose. The counsel for the petitioner contractor further contended that while adopting the formula

of increase the Arbitrator has excluded the costs indices of steel and cement. It is contended that once delay was attributed to the respondent

DDA, the damage to the petitioner contractor was implicit and the award of the Arbitrator in that respect need not be interfered with. It is further

pointed out that the contract in question is of before the time of introduction of Clause 10CC added in the subsequent contracts of DDA. Reliance

in this regard is placed on Jagat Ram Trehan and Sons Vs. DDA, where objections to the amount awarded for delay in a contract without Clause

10CC were dismissed. The counsel for the petitioner contractor in this regard also refers to:

(i) State of Rajasthan v. Puri Construction Ltd. 1995 (22) Arb. LR 1 (SC) laying down that the Arbitrator is the final arbiter for the disputes

between the parties and it is not open to challenge the award on the ground that the Arbitrator has drawn his own conclusion or has failed to

appreciate the facts and where the plea of the award being bad for award of lump-sum damages in the absence of any material showing actual loss

suffered by the contractor was dismissed.

(ii) Uttam Singh Duggal and Co. Vs. Union of India and Others, where also the objection to the award on the ground of the same being without

proof of damages were dismissed holding the same to be a matter of appreciation of facts.

(iii) N.D.R. Israni Vs. Delhi Development Authority, where award on the basis of cost index was upheld.

(iv) Bedi Construction Co. Vs. Delhi Development Authority, where also objection to the award on the basis of the same being not in accordance

with Clause 1 0C was dismissed holding the assessment to be under Clause 10C.

37. Clause 10C in the contract in the present case, is identical to that in the judgments of this Court in M/s Republic Construction Co. and Verma

Construction Co. (supra). The same provided for escalation during the progress of the works. The said clause is not limited only to the escalation

during the stipulated period of the contract. The work was in progress during the period of extension, attributable whether to the petitioner

contractor or to the respondent DDA. Clause 1 0C does not admit of any distinction in progress of the works within the stipulated period or the

extended period. In any case, upon extension, the extended period is deemed to be the modified stipulated period and the escalation thereunder

would be governed by Clause 1 0C. To the same effect is the recent judgment in S.J. Chaudhary Vs. CBI, , also laying down that escalation even

during extended period of contract has to be under Clause 1 0C and without proof on record no amount can be awarded. The award on Claim

No. 18 is admittedly not in accordance with the Clause 10C, though found to be covered by the said clause. The same thus cannot be sustained.

The Arbitrator is a creature of the contract and cannot operate outside the contract. I thus allow the objection to the award on Claim No. 18 and

set aside the award to that extent.

Re: Claim No. 2 1

38. The counsel for the petitioner contractor claimed Rs. 15,000/- for replenishment of loss sustained on account of works of DESU while laying

the trenches. The Arbitrator has awarded Rs. 5,000/- against the said claim. The counsel for the respondent DDA has challenged the award as

being without any basis and has also contended that the claim for loss on account of action of DESU should have been pursued against DESU and

not against the respondent DDA.

39. DESU was also permitted on the site by the respondent DDA only. The view taken by the Arbitrator is a possible view and cannot be said to

be perverse and calls for no interference. The objections to award under said claim are dismissed.

Re: Claim No. 22

40. The petitioner contractor had claimed Rs. 4,36,800/- for site expenses and other overheads for the extended period of the contract. The claim

has been allowed to the extent of Rs. 1,42,800/-.

41. The counsel for the respondent DDA has besides the arguments raised with respect to the award under Claim No. 18 challenged the award as

being arbitrary and without any proof or basis. It is also contended that the agreement items included the overhead. Per contra the counsel for the

petitioner contractor has in this regard relied on Mr. M.L. Mahajan Vs. D.D.A. and Another, where this Court did not find anything objectionable

or perverse in the award on such basis.

42. The matter being no longer res-integra, the objections to the award under the said claim are to be dismissed.

Re: Claim No. 23

43. The petitioner contractor had claimed Rs. 2,00,000/- for doing the work of cement paint over a roughcast plaster. The Arbitrator has found

that there is no item in the DSR for such specification and the rate in the DSR is for painting on a smooth surface only. Finding the CPWD

specification for providing 20% increase in case of corrugated surface and holding that the consumption of cement paint would be double over a

rough surface than over a plain surface, allowed the claim in toto.

44. The counsel for the respondent DDA has contended that it was known to the petitioner contractor that the work of painting over rough

surface/grit finish, was to be carried out. Attention in this regard is invited to Clause 9 of the agreement together with schedule to the agreement.

45. I do not find the contract or the schedule thereto to have provided for cement paint on grit finish. The respondent DDA having admittedly

required grit finish with cement paint thereon cannot object to the award and no perversity is found therein. The objections are dismissed.

Re: Claim No. 26

46. The petitioner contractor claimed Rs. 4,50,000/- for final bill of undisputed items. The said claim has been allowed to the extent of Rs.

3,64,619/-.

47. The counsel for the respondent DDA has again contended that there is no basis for the awarded figure. It is also contended that the rebate for

payment of final bill within 6 months has been wrongly disallowed.

48. The award aforesaid is factual and does not admit of any interference. Suffice, it is to state that no perversity is shown therein. The objections

are dismissed.

Re: Claim No. 33 for interest

49. The counsel for the respondent DDA has objected to the high rate of interest awarded and has relied on recent judgments where the rate of

interest has been reduced to 8% to 10%. Per contra the counsel for the petitioner contractor has justified the rate of interest owing to long passage

of time and the transaction being of a commercial nature.

50. Though the proceedings for making the award the Rule of the Court and the objections preferred against the award, have remained pending for

long but it cannot be said to be for reasons attributable to the respondent DDA. It also cannot be said that the respondent DDA has in the

interregnum used the money found due to the petitioner contractor commercially. In the circumstances, considering the majority of the recent

judgments providing for lower rates of interest in view of the falling rates of interest, the interest pendente lite is reduced from 15% to 6% and

interest from the date of the award and till the date of payment/decree from 18% to 9% per annum.

51. The counsel for the petitioner contractor has also contended that the Bank Guarantee furnished by the petitioner contractor with the

respondent DDA has not been released and an order therefore may also be made.

52. In view of the findings above, the award as modified above is made Rule of the Court and decree is passed in terms thereof. The petitioner

contractor is also granted interest u/s 29 at the rate of 9% per annum. The respondent DDA is also directed to release the bank guarantee

furnished by the petitioner contractor within six weeks.

Under the circumstances, no order as to costs.