Union of India (UOI) Vs Pyare Lal and Sons and Another <BR> Pyare Lal and Sons Vs Union of India (UOI) and Another

High Court Of Punjab And Haryana At Chandigarh 26 Oct 2010 C.R. No''s. 1602 of 1999 and 918 of 2000 (2010) 10 P&H CK 0075
Bench: Single Bench

Judgement Snapshot

Case Number

C.R. No''s. 1602 of 1999 and 918 of 2000

Hon'ble Bench

Hemant gupta, J

Judgement Text

Translate:

Hemant gupta, J.@mdashThis order shall dispose of C.R. No. 1602 of 1999 filed by the Union of India (hereinafter referred to as ''the Agency'')

and C.R. No. 918 of 2000 filed by M/s Pyare Lal and sons (hereinafter referred as ''the Contractor''). Both the revision petitions arise out of an

order passed by the learned trial Court 20.10.1997 making Award dated 29.12.1993 as rule of court. In appeal, the order passed by the learned

trial Court was modified and the Award in respect of Claim Nos. 1, 3 & 6 were set aside and the Award in respect of remaining Claims was made

rule of the Court.

2. The Agency is aggrieved against the Award being made rule of the court in respect of Claim Nos. 2 & 5, whereas the Contractor is aggrieved

against the Award being set aside in respect of Claim Nos. 1, 3 & 6

3. The Agency invited tenders for special repairs to O.T.M. accommodation at Chandimandir Cantonment on 17.01.1989. The tender submitted

by the Contractor was accepted. The total amount involved in the contract was Rs. 4,86,684/-. The work was to be completed within six months

from the date of commencement of the work. The work commenced on 07.02.1989, but could not be completed on or before 06.09.1989. The

period was extended upto 12.03.1990, but the work could not be completed even upto the extended date. The Agency cancelled the contract on

22.05.1990. The remaining work was got executed through some other Contractor. Since the dispute arose between the parties, Shri P.D.

Sharma, Superintending Engineer, was appointed as the sole Arbitrator in view of the arbitration clause in the agreement between the parties. The

Arbitrator announced his award and awarded the following amount against each Claim:

Claim Amount ClaimedDescription of Claim Amount Awarded

Number

1 `1,00,000/- For damages suffered on account of illegal Rs. 25,000/-

cancellation of contract when the work was in

progress

2 Rs. 50,000/- For loss suffered on account of non-handling 10,000/

over the dismantled and demolished Materials

of building No.T/3776 & Tent Plinths

3 Rs. 2,00,000/- For balance payment for work done includingRs. 70,674.18

escalation in wages and cost of materials

4 Rs. 25,000/- For work done in buildings not forming part NIL

of the contract agreement

5 Rs. 1,00,000/- For reimbursement of damages on account ofRs. 85,000/-

breach of contract by the Union of India

including illegal cancellation, delay in issue of

schedule �B� Stores, delay in handing

over sites, non-payment for escalation in cost,

delay and restrictions in payment of running

bills, non-supply of water due to scarcity,

non-ordering provisional quantities, delay in

measurement of work resulting in

underpayments etc. resulting in prolongation

of contract period.

6 Rs. 50,000/- For on account of loss suffered due to non- Rs. 50,000/-

payment and delay of running and final bill

7 Rs. 75,000/- For payment of materials and tools and NIL

plants.

8 For interest on above amounts unduly 12%

withheld @ 18% p.a.

9 Rs. 20,000/- For cost of reference to arbitration NIL

4. Learned first Appellate Court found that the claim awarded by the Arbitrator under Claim Nos. 1, 3 & 6 are, in fact, the claims awarded in the

Claim No. 5 and, thus, the Arbitrator has no power to allow duplicate claims on the same grounds and reasoning. Learned first Appellate Court

also found that the Contractor was paid Rs. 3,60,089/- for the work done by it, whereas on completion of total work, the Contractor would have

got Rs. 4,86,684/- in lump sum. But the Arbitrator has awarded him Rs. 2,40,674.18, which is more than the contract amount. Thus, the appeal

filed by the Agency was accepted partly.

5. Learned Counsel for the Contractor has vehemently argued that the finding recorded by the learned first Appellate Court that the Contract has

claimed Claims on the same account under different heads is incorrect. It is contended that each of the Claim of the Contractor is separate and

distinct and that finding recorded by the learned first Appellate Court is incorrect.

6. On behalf of the Agency, Ms. Shahi argued that the primary claim of the Contractor is on account of delay in handing over the sites, delay in

issue of Schedule ''B'' or for delay in completion of the contract. It is contended that for such delay the Contractor is not entitled to claim any

amount in terms of the specific Clause-11 of the General Conditions of the Contract.

7. Reliance is placed upon a judgment of Hon''ble Supreme Court reported as Ramnath International Construction Pvt. Ltd. Vs. Union of India

(UOI) and Another, and on an order passed by this Court in C.R. No. 2796 of 2000 titled ""Manohar Lal & Sons v. Union of India and Ors.

decided on 03.08.2010.

8. Before preceding further, the relevant clauses of Clause-11 of the Agreement are to be extracted. The said clause reads as under:

11. Time, Delay and Extension -

(A) Time is essence of the contract and is specified in the contract documents or in each individual works order.

As soon as possible after contract is let or any substantial Works Order is placed and before work under it is begun, the G.E. and the contract

shall agrees upon a Time and Progress Chart. The Chart shall be prepared in direct relation to the time stated in the contract documents or the

Works Order for completion of the individual items thereof and / or the contract or Works Order as a whole. It shall indicate the forecast of the

dates for commencement and completion of the various trade processes or sections of the work, and shall be amended as may be required by

agreement between the G.E. and the contract within the limitation of time imposed in the contract documents or Works Order. If the Works be

delayed:

i) by force majeure, or

ii) by reason of abnormally bad weather, or

iii) by reasons of serious loss or damage by fire or;

iv) by reason of civil commotion, local combination of workmen, strike or lockout, affecting any of the trade employed on the work, or

v) by reason of delay on part of nominated sub contractors, or nominated suppliers which the contractor has in the opinion of G.E. taken all

practicable steps to avoid, or reduce, or,

vi) by reason of delay on the part of contractors or tradesmen engaged by Government in executing works not forming part of the contract, or

vii) by reason of any other cause which in the absolute discretion of the Accepting Officer is beyond the contractor''s control;

then in any such case, the officer hereinafter mentioned may make fair and reasonable extension in the completion dates of individual items or

groups of items of Works for which separate periods of completion are mentioned in the contract documents or Works Order, as applicable.

xxx xxx xxx

(B) If the works be delayed:

(a) by reason of non availability of Government stores shown in Schedule ''B'' or

(b) reason of non availability or breakdown of Govt. Tools and Plant listed in Schedule ''C''

Then, in any such case notwithstanding the provisions hereinbefore contained, the G.E. may in his discretion grant such extension of time as may

appear reasonable to him, and the contractor shall be bound to complete the Works within such extended time. In the event of the contractor not

agreeing to the extension granted by the Garrison Engineer, the matter shall be referred to the Accepting Officer (or C.W.E. in case of contract

accepted by Garrison Engineer) whose decision shall be final and binding.

(C) No claim in respect of compensation or otherwise, howsoever, arising, as a result of extensions granted under conditions (A) and (B) above

shall be admitted.

9. A perusal of the brief description of the Claims reproduced above would show that Claim No. 3 is for balance payment for work done including

escalation in wages and cost of materials. Similarly, Claim No. 5 is in respect of reimbursement of damages on account of breach of contract

including illegal cancellation, delay in issue of schedule ''B'' Stores, delay in handing over sites, non-payment for escalation in cost, delay and

restrictions in payment of running bills, non-supply of water due to scarcity, non-ordering provisional quantities, delay in measurement of work

resulting in underpayments etc. Claim No. 6 is again on account of loss suffered due to non-payment and delay of running and final bill. Therefore,

Claim Nos. 3, 5 & 6 are on account of delay in issuances of schedule ''B'' stores, handing over sites, escalation in wages and cost of materials on

account of delay or loss suffered on account of non-payment of escalation in cost and delay and restrictions in payment of running bills. Clause

11(c) of the Contract agreement prohibits compensation or otherwise as a result of extension granted under Clauses (a) and (b) of Clause 11 of

the Contract. A perusal of the statement of claim further shows that the Contractor was granted extension in completion of project. Once, the

Contractor has been granted extension in completion of project, therefore, by virtue of Clause 11 (c) of the Contract Agreement, the Contractor

cannot claim compensation for delay in completion of the work. Not only the Contractor has claimed the amount on account of delay under Claim

Nos. 3, 5 & 6. Though the Contractor has claimed balance payment for the work done including escalation of wages under Claim No. 3, but since

the Arbitrator has given consolidated award under Claim No. 3, it is impossible to determine the amount awarded to the Contractor for the

balance work or for escalation of wages. Therefore, being the consolidated amount the entire claim is liable to be set aside. Similarly, under Claim

No. 5, the Contractor has claimed reimbursement of damages on account of breach of contract and delay of schedule ''B'' etc. Even the amount

determined under Claim No. 5 is not determinable as to how much amount is towards breach of contract and how much amount is towards delay

in issuance of schedule ''B'' stores. Therefore, the entire claim is liable to be set aside.

10. The learned first Appellate Court has set aside Claim Nos. 3 & 6 alone being duplicate claims, but in fact Claim No. 3, 5 & 6 all relate to

delay in completion of the work and, thus, compensation is not payable under any of these heads. This is the view taken by this Court in M/s

Manohar Lal''s case (supra) relying upon the judgment referred to by the learned Counsel for the Agency, wherein it was held to the following

effect:

However, in the present case, the Arbitrator has given Award claim wise. Claim No. 11 as reproduced above primarily falls within the scope of

Clause (B) or Clause (A)(vii) of condition No. 11 of the contract agreement. Claim No. 11 is specifically in respect of compensation on account of

delay in handing over site and other ancillary matter. Such delay in handing over site falls within Clause 11(C) of the contract which contemplates

that no compensation shall be admissible to the contractor. Clause (C) of the agreement is specific and is to the effect that no claim in respect of

compensation or otherwise arising as a result of extensions granted under conditions (A) and (B) shall be admitted. It is the terms of the agreement

which has to be kept in view while considering the claim of the contractor. Since the contract agreement specifically prohibit compensation on

account of delay falling in Clauses (A) and (B) of Clause 11 of the agreement, therefore, the petitioner is not entitled to compensation on account

of delay in completion of the work.

11. The argument of the learned Counsel for the Contractor that such amount is not claimed in none of the other claims, therefore, the reasoning

given by the first Appellate Court that the Contractor has claimed same amount under various claims is not sustainable. Claim No. 1 is for damages

on account of illegal cancellation of contract when the work was in progress.

12. I am of the opinion that the finding recorded by the learned first Appellate Court that amount claimed under Claim No. 1 is also amount

claimed under different heads, is not sustainable. The Contractor has not claimed damages on account of illegal cancellation of contract under any

other head. In view of the said fact, the order passed by the learned first Appellate Court not making the Award as rule of court in respect of

Claim No. 1 is not sustainable.

13. Therefore, both the revisions are partly accepted. Award of the Arbitrator in respect of Claim Nos. 3, 5 & 6 is set aside, whereas the Award

dated 29.12.1993 is ordered to be made rule of court in respect of Claim Nos. 1, 2 and 8 only. The Contractor shall be entitled to interest at the

rate of 12% from the date of decree till realization as well.

14. With the said observations, both the revision petitions stands disposed of.

From The Blog
Madras High Court to Hear School’s Plea Against State Objection to RSS Camp on Campus
Feb
07
2026

Court News

Madras High Court to Hear School’s Plea Against State Objection to RSS Camp on Campus
Read More
Delhi High Court Quashes Ban on Medical Students’ Inter-College Migration, Calls Rule Arbitrary
Feb
07
2026

Court News

Delhi High Court Quashes Ban on Medical Students’ Inter-College Migration, Calls Rule Arbitrary
Read More