Vijeta Projects and Infrastructures Ltd. Vs The State of Jharkhand and Others

Jharkhand High Court 15 Feb 2011 L.P.A. No. 33 of 2011 (2011) 1 JLJR 528 : (2011) 2 JCR 326
Bench: Division Bench
Result Published

Judgement Snapshot

Case Number

L.P.A. No. 33 of 2011

Hon'ble Bench

Bhagwati Prasad, C.J; D.N. Patel, J

Final Decision

Dismissed

Judgement Text

Translate:

1. Heard learned Counsel for the parties.

2. The tender which was issued in the year 2008 has not been finalized even today. In the meantime, the State Government has decided not to

pursue the matter any further in relation to tender, issued earlier and has sought to re-advertise the tender.

3. The Appellant is aggrieved of this. The Appellant''s argument is that the recommendation which was placed before the Adviser to the Governor

was not to the effect that there should be re-tender and in that view of the matter, this order of the Adviser to the Governor cannot be considered

to be a reasoned order and it is, thus, an arbitrary order and such arbitrary orders are not in accordance with law as has been laid down by the

Supreme Court in the case of Union of India and Others Vs. Dinesh Engineering Corporation and Another etc., .

4. We have looked into the note which precedes the final order of the Adviser to the Governor and in that note, we find that before tender was

issued, there was no technical sanction available for the proposed work and as such the opinion expressed in the note is in conformity with the

earlier Vigilance Commissioner''s report dated 6.4.2010 produced herewith at page-122. When we find that the tender process was initiated

without there being a valid technical sanction, it cannot said that a tender therefore could be preceded with, when initially there was no technical

sanction and proper evaluation. The notice preceding the order of the Adviser to the Governor notices many drawbacks and inconformities in the

process of issuing tender. In view of the aforesaid, when a tender which was issued in the year 2008 has not become final till date, the

reasonableness requires that such tender should not be allowed to remain in existence because the period of 2008 to 2011 has seen too much

fluctuations in financial sector and in that view of the matter, it would not be appropriate for this Court to enter into the question because there are

reasons available on record for re-tendering and reasonableness also require that after such a long time when a tender is not finalized, the same

should be re-advertised.

5. In that view of the matter, we find no illegality in the order of the learned single Judge. There being no force, this appeal is accordingly dismissed.

From The Blog
Moti Ram Deka & Ors vs General Manager, N.E.F. Railways & Ors (1963)
Oct
19
2025

Landmark Judgements

Moti Ram Deka & Ors vs General Manager, N.E.F. Railways & Ors (1963)
Read More
M/s. Orissa Cement Ltd. & Others vs State of Orissa & Others (1991)
Oct
19
2025

Landmark Judgements

M/s. Orissa Cement Ltd. & Others vs State of Orissa & Others (1991)
Read More