JAYA SHREE INSULATORS Vs West Bengal State Electricity Board

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION 19 Apr 2002 (2002) 04 NCDRC CK 0032
Result Published

Judgement Snapshot

Hon'ble Bench

D.P.Wadhwa , Rajyalakshmi Rao , B.K.Taimni J.

Final Decision

Complaint dismissed

Judgement Text

Translate:

1. IN this complaint against the opposite party-West Bengal State Electricty Board following reliefs have been claimed :

"Your petitioner therefoe most humbly prays that the learned Commission may not (be) graciously be pleased to pass the following orders : (a) The respondent be directed to make payment of damages assessed at Rs. 44,76,60.000/- as pleaded in paragraph 9 hereinabove. (b) Alternatively an inquiry into loss and damages suffered by your petitioner, and upon such inquiry, direction be given to the respondent to make payment of such sum as may be found due and payable by the respondent Board to your petitioner. (c) INterest @ 24% p.a. on the said sum of Rs. 44,76,60,000/- or such other sum as may be found due and payable by the said respondent Board to the petitioner for the loss and damages. (d) The respondent be directed to ensure that there is no interruption in power supply and fluctuation of voltage are affected. (e) Respondent be directed to ensure that the deficiency in service does not affect. (f) Costs of and incidental to this application be borne and paid by the respondent Board. (g) Such further and/or other order or orders be made and/or direction or directions be given as this learned Commission may deem fit and proper".



2. COMPLAINT is in initial stage. So far written version has not been filed by the respondent-opposite party.

We asked the learned Counsel for the complainant as to how the figure of damages of over Rs. 44.00 crores has been arrived at and how he is going to prove the alleged loss suffered by the complainant. He referred to (i) para 3 of the complaint where it is mentioned that there was expenditure of about Rs. 25.00 lakhs for providing dedicated 33 KV line and 33 KV S/S exclusively for the unit of the complainant; (ii) para 4 where complainant gave a bank gurantee of Rs. 18,60,500/-; and (iii) para 5-it is mentioned that there was production loss aggregating to a sum of Rs. 22,38,30,000/-.

All this would show that a great deal of evidence will be required both oral and documentary to prove such a huge loss as claimed by the complainant. It was submittd by learened Counsel for the opposite party that interpretation of agreement for the supply of electrical energy at high voltage will have to be gone into. In our view it is not a case which can be decided in our summary jurisdiction. Supreme Court in the case of Synco Industries v. State Bank of Bikaner & Jaipur and Others, observed that where complicated questions of law and facts are involved Forum under the Consumer Protection Act may not be a proper Forum to dispose of such a case in summary fashion. It was also observed that a Civil Court would be right place to decide the issue involved in that case and it went further to add that the complainant did not file the complaint before the Civil Court to start with because, before Consumer Forum, any figure in damages can be claimed without having to pay Court-fees and that this, in that sense, was an abuse of the process of the Consumer Forum. Accordingly, this complaint is dismissed with the liberty to the complainant to approach Civil Court or any other Forum for the reliefs claimed.



3. WE may also notice that complaint was filed on 20.10.1997. Complainant can take advantage of provision of Section 14 of the Limitation Act. In this connection, we refer a decision of the Supreme Court in the case of Laxmi Engineering Works v. PSG Industrial Institute, II (1995) CPJ 1 (SC)=(1995) 3 SCC 583, where while dismissing the appeal the Court observed as under :

"If the appellant chooses to file a suit for the relief claimed in these proceedings, he can do so according to law and in such a case he can claim the benefit of Section 14 of the Limitation Act to exclude the period spent in prosecuting the proceedings under the Consumer Protection Act, while computing the period of limitation prescribed for such a suit."

Complaint dismissed.
From The Blog
Quick Checklist: Start a Company in the USA from India
Nov
09
2025

Court News

Quick Checklist: Start a Company in the USA from India
Read More
Supreme Court: Release Deed Ends Coparcener Rights in Joint Family Property; Unregistered Settlements Valid to Show Severance
Nov
09
2025

Court News

Supreme Court: Release Deed Ends Coparcener Rights in Joint Family Property; Unregistered Settlements Valid to Show Severance
Read More