@JUDGMENTTAG-ORDER
1. Leave granted.
2. This Court has heard the learned Counsel for the parties regarding relief claimed by the appellants.
3. The appeal is directed against order dated August 5, 2008, rendered by the High Court of Bombay at Goa in Miscellaneous Civil Application No. 595 of 2008, which was filed in Writ Petition No. 403 of 2007 by which the parties have been directed to maintain status quo in respect of construction within 50 to 100 meters of High Tide Line on survey Nos. 11/1 and 101/1 of Bambolim village, Goa, till the matter is finally heard by the Court.
4. The record would indicate that after purchase of the lands in question the appellants applied to the Panchayat for sanction of plans for construction of hotel. The permission was granted by the village Panchayat on November 26, 1993. The Ministry of Environment and Forests had issued a notification called Coastal Regulation Zone for regulating the development of areas within 500 meters of the coast. The said notification was amended on August 16, 1994 reducing the "No Development Zone" to 50 meters from 100 meters. The appellant No. 1 had submitted amended plans seeking permission to put up construction leaving 50 meters "No Development Zone". The Village Panchayat had granted the permission sought for. In
5. It may be mentioned here that in the Public Interest Litigation MOEF has filed reply confirming its stand taken in the petition filed by the appellants and, therefore, the High Court rejected the application made in PIL for interim relief on September 12, 2007. The High Court declined to grant interim relief noting that the Central Government had itself referred the matter to National Coastal Zone Management Authority. The Court, while declining to grant interim relief, directed the said Authority to consider the matter after giving personal hearing to all parties. The record shows that the said Authority gave hearing to all the parties and has treated the project of the appellants as an ongoing project. By the impugned order the High Court has directed the parties to maintain status quo regarding construction because according to the High Court it was admitted by one of the directors of the appellants that from 1997 to 2005 there was no construction activity and the Apex Court has struck down amendment restricting the NDZ to 50 meters only.
6. As noted earlier, the project of the appellants is treated to be an ongoing project. The decision dated October 30, 2007 rendered by the National Coastal Zone Management Authority is in favour of the appellants, which is now challenged by the respondents in PIL by amending the petition. Without considering the validity of the same the impugned interim direction should not have been granted, more particularly, when interim relief was earlier refused to the respondent. Grant of stay of construction activity would result into considerable loss to the appellants who have invested huge amount in the project. On the facts and in the circumstances of the case this Court is of the opinion that interest of justice would be served if the appellants are permitted to complete incomplete construction at their own risk and cost.
7. For the foregoing reasons the appeal partly succeeds. The impugned order is set aside. During the pendency of the petition before the High Court, the appellants are permitted to complete the incomplete construction work done by them at their own risk and cost. The High Court is requested to dispose of the matter on merits without being inhibited by this order granting interim relief to the appellants as early as possible and without any avoidable delay.
8. No costs.