M/s. Mehul Realtors Private Ltd. Vs Mumbai Municipal Corporation of Gr. Mumbai and Others

Bombay High Court 17 Feb 2014 Writ Petition No. 1522 of 2013 (2014) 4 BomCR 683
Bench: Division Bench
Result Published
Acts Referenced

Judgement Snapshot

Case Number

Writ Petition No. 1522 of 2013

Hon'ble Bench

Anoop V. Mohta, J; A.A. Sayed, J

Advocates

D.H. Mehta and Mr. S.B. Pawar and Ms. Swati Sawant instructed by S.K. Legal Associates, for the Appellant; Komal Punjabi for Respondent Nos. 1 to 3, Mr. V.S. Pande instructed by . Mr. S.U. Pandey for Respondent No. 4 and Mr. Hemant B. Dalal, Respondent No. 5, for the Respondent

Final Decision

Disposed Off

Acts Referred

Mumbai Municipal Corporation Act, 1888 - Section 354 522

Judgement Text

Translate:

Anoop V. Mohta, J.@mdashIn view of urgency, heard finally. The Petitioner as owner/landlord of the property bearing C.T.S. nos. 1211, 1211/1

to 8 with structure/building standing thereon known as ""Pandya House"" on plot no. 84-B of TPS III, situate at Sarojini Road, Vile Parle (West),

Mumbai (for short the ""property"") has filed the present Petition and prayed for direction against Respondent nos. 1 to 3 (Mumbai Municipal

Corporation and its officers) to take immediate steps/action for vacating and demolishing the dilapidated structure basically room premises nos. 1

and 11.

2. There is no dispute with regard to the dilapidated condition of the building in question and the related notices issued by the Corporation since

2008 onwards. Out of 14 structures/rooms, 13 rooms are already vacated by the occupants by settling the matter with the Petitioner-owner.

Room premises no. 11 which was also the subject-matter of the Petition has been demolished in view of settlement. The dispute remains with

regard to room premises no. 1 which Respondent nos. 4 and 5 are claiming to be in joint possession along with sister Chandrika. Admittedly, suits

are pending in the Small Causes Court filed by Respondent no. 4 for a declaration that the tenancy of the room along with appurtenant disputed

land in question having an area of 59.48 sq. mtrs. and land having an area of 682 sq. mtrs. Respondent no. 5 has filed Suit no. 611 of 2011 in the

Small Causes Court, Bandra, with regard to room no. 15 along with terrace area admeasuring 1425 sq. ft. So far as the present Petition is

concerned, we are dealing with room no. 1 only as the statement is made that room no. 15 is already demolished. We are not at this stage dealing

with the same. Let parties contest their respective claim in the pending proceedings. It is made clear that the Petitioner will abide by the decision so

given by the Court in the suits filed by Respondent no. 4/5.

3. This matter was adjourned from time to time for settlement on the lines of settlement terms which the Petitioner has done with other occupants

who have already vacated the premises. Respondent no. 4, who is present in the Court through the Advocate is willing to settle the matter on

condition that the rights and contentions so raised in the civil suit in the Small Causes Court be kept open for adjudication/decision in every respect.

He, on this, is willing to vacate the premises within four weeks.

4. The Petitioner, as recorded in order dated 20 January 2014, is willing to file Consent Terms and/or to provide permanent alternate

accommodation on tenancy basis, in lieu of room no. 1 having an area of 59.48 sq. mtrs. as early as possible even before four weeks if the

Respondents vacate the premises.

5. Respondent no. 5 who appears in person filed his affidavit-in-reply and agitated grievances which he has already raised in the pending suits. He

is not willing to settle the matter. The disputed questions of fact raised by Respondent no. 5 just cannot be gone into at this stage of the

proceedings in the present Writ Petition specifically in view of the fact of dilapidated condition of the building/premises and except Respondent

nos. 4 and 5, all have already vacated the premises and the Petitioner has already demolished all those rooms except room no. 1 in question.

6. There is no serious dispute with regard to notices issued by the Corporation for demolition of the building in question, including that of section

354 of the Mumbai Municipal Corporation Act dated 09 May 2013. In view of the above position, it is difficult for the Court to overlook the

observations/decision given by this Court in The Tadeshwar Wadi Co-operative Housing Society Ltd. Vs. The State of Maharashtra Mantralaya

and Others, which read thus:

18. Considering the setting in which the provisions are placed and the purport of those provisions, we have no manner of doubt that even though

the primary obligation is on the owner and occupier to act upon the requisition of the Corporation issued u/s 354 of the Act in relation to the

structure in ruins or likely to fall, but that does not extricate the Corporation from its duty to remove such structure in public interest at the earliest.

In doing so, the Corporation may have to resort to eviction of the occupants but that drastic action would be of a far lesser degree than the loss or

damage to be caused in the neighborhood on account of sudden collapse of the dilapidated and dangerous building. Indeed, in the unreported

decision in M/s. Whiz Enterprises Pvt. Ltd. (supra), the efficacy of these provisions has not been specifically dealt with. However, for the reasons

already noted, we have no hesitation in taking the view that the petitioner-Society is justified in seeking direction against the Corporation for its

inaction to take successive notices issued u/s 354 of the said Act to its logical end by removing the dilapidated and dangerous structure referred to

therein. For facilitating the officials of the Corporation to discharge this duty, we have no manner of doubt that the police authorities would extend

adequate logistical support to them, if so demanded and as may be warranted, which is the obligation of the police authorities u/s 522 of the Act.

19. Accordingly, we allow this Writ Petition and direct the Corporation to take the last notice issued to the Petitioner by the Corporation dated

21-3-2012 as also the individual notices dated 11-6-2012 given to the occupants, who has still not vacated the premises in their possession, to its

logical end, in accordance with law, forthwith and in doing so, may take assistance of the local police authorities, who are obliged to provide all

logistical support to the officials of the Corporation.

7. Therefore, by keeping all the points open and issues raised by Respondent nos. 4 and 5, in the interest of all, we are convinced that this is a case

where the Respondent-Corporation needs to take steps in accordance with law, including drastic action in case the occupants, in spite of such

situation, have not vacated the premises in their possession of the dilapidated building in question if required it to be demolished at earliest. The

resistance by one occupant as referred to above should not prevent the Court, as well as the Respondent-authorities to take action though their

dispute with regard to area of room/premises is pending. The family dispute also with regard to occupants of room no. 1 in question just cannot be

gone into and/or decided in the present Writ Petition. The Petitioner even otherwise is not under an obligation to provide alternate accommodation

to all occupants of one room, separately. However, the Petitioner is under an obligation to provide only one accommodation being legal heirs of

the tenants and/or occupations. There is no question of providing three different accommodations to all the occupants as claimed by Respondent

nos. 4 and 5 and/or sister as referred to above.

8. For the above reasons, we are disposing of the present Petition by directing the Corporation to take action against those occupants who have

still not vacated the premises, in accordance with law, if necessary, by taking assistance of the local police authorities who are to provide all

supports to the officers of the Corporation.

9. However, in the interest of justice, we are still inclined to grant four weeks'' time to vacate the premises to the Respondent nos. 4 and 5 and the

sister and/or settle the matter.

10. It is made clear that pending decision for the above reasons, the Petitioner and/or Corporation is not prevented from taking action of taking

possession of the property (room no. 1) with surrounding land. The Petitioner is at liberty to proceed for demolition and/or construction on the suit

property i.e. C.T.S. nos. 1211, 1211/1 to 8 with the structure/building standing thereon known as ""Pandya House"" on plot no. 84-B of TPS III,

situate at Sarojini Road, Viole Parle (West), Mumbai. The Petitioner is at liberty to develop the property in accordance with law.

11. It is necessary to observe that the Petitioner has already settled the matter and paid substantial amount/compensation to other occupants. The

investment so made and the development of the property which they have decided to develop just cannot be halted at this stage at the instance of

one occupant who even otherwise will not be in a position to compensate the losses/damages suffered by the Petitioner because of such delay in

development of the property in question. Therefore, the balance of convenience equally lies in favour of permitting the Petitioner to proceed with

the development. However, it will be subject to decision with regard to rights of Respondent nos. 4 and 5 which need to be adjudicated in the

Court in question.

12. The Petitioner/Respondent Corporation to take action as recorded above if Respondent nos. 4 and 5 fail to vacate the premises within four

weeks. The Petition is accordingly disposed of. No costs. At this stage, Respondent no. 5 prays for stay of this order. Respondent no. 4 has not

prayed for such stay. For the above reasons itself and as we have already granted four weeks time to vacate the premises/rooms, we decline to

grant stay to this order. Prayer for stay is, therefore, rejected.

From The Blog
Supreme Court Halts GST Assessment on Joint Development Deals
Oct
28
2025

Story

Supreme Court Halts GST Assessment on Joint Development Deals
Read More
Supreme Court Explains Demurrer Law in Neelkanth Realty Case
Oct
28
2025

Story

Supreme Court Explains Demurrer Law in Neelkanth Realty Case
Read More