Dipankar Datta, J.@mdashThe Kolkata Municipal Corporation (hereafter the Corporation) sanctioned a building permit in favour of the petitioner
for the purpose of raising construction on premises No. 23A/660, Diamond Harbour Road, Kolkata (hereafter the said premises) vide No. BS-
124 on 28.10.1999. The plan was valid till 27.10.04. It is the case of the petitioner that on 20.3.03 he intended to start construction said premises
but was prevented from doing so by the concerned police authorities. Being aggrieved thereby, he had preferred a writ petition before this Hon''ble
Court being W.P. 5188 (W) of 2003. On 22.4.03, a learned Judge of this Court for reasons recorded in the order granted liberty to the petitioner
to carry on construction work at the premises in question strictly in accordance with the sanctioned building plan until further orders. The petitioner
was also given liberty to seek assistance from the police for protection of his life and property as well as the safety and security of the labours who
would be engaged in construction work. The police authorities were directed to render adequate police assistance, if sought for. However, it was
recorded that pendency of the writ petition would not prevent the Corporation from proceeding with the proposal for acquisition of the said
premises and/or to take any further step in respect of the construction work thereat in accordance with law.
2. Immediately after the aforesaid order was passed, the Executive Engineer (Building), Borough No. X of the Corporation vide his letter dated
25.4.03 informed the petitioner that the Corporation had already taken steps for acquisition of the said premises for a park and hence it was felt
prudent to withhold the building sanction plan vide No. 124 (B-X)/99-2000 dated 28.10.99 for the time being and no construction work will be
allowed on the abovenoted premises"". According to the petitioner, this letter was served on him on 25.4.03 when he had been to the said premises
for the purpose of raising construction in terms of the sanctioned building plan. As a consequence, the petitioner could not raise construction.
3. This was followed by a notice u/s 4(1) of the Land Acquisition Act, 1894 dated 23-10.2003 issued to the petitioner by the 1st Land Acquisition
Collector, Calcutta pursuant whereto the petitioner filed an objection. However, by letter dated 8.12.04 written by the Assistant Secretary to the
Government of West Bengal, Land and Land Reforms Department, the 1st Land Acquisition Collector, Calcutta was requested to drop the land
acquisition proceeding initiated for acquisition of the said premises and an action taken report was directed to be submitted. This was followed up
by a letter of the Land Acquisition Collector dated 21.7.05 whereby he confirmed to the petitioner''s lawyer that no proposal to initiate further land
acquisition proceeding for acquiring the said premises had been received by his office.
4. These facts in the background, the petitioner vide his representations dated 7.7.05 and 11.8.06 had requested the Mayor of the Corporation to
permit him to resume construction excluding the time for which operation of the building plan was withheld by the order dated 25.4.03 issued by
the Executive Engineer and also to revive the building plan by granting extension thereof. No action having been taken by the Corporation, the
petitioner has approached this Court with the prayer to direct the Corporation authorities not to give effect to the impugned notice dated 25.4.03
issued by the Executive Engineer and also for rescission, cancellation and/or setting aside of the same and to revive the sanctioned building plan
dated 28.10.99.
5. Mr. Ali, learned Senior Counsel appearing for the petitioner submitted that undisputedly the building plan which was to remain valid till 27.10.04
was not allowed to be operative with effect from 25.4.03 and, therefore, this Court ought to direct the Corporation to permit the petitioner to raise
construction on the basis thereof after excluding the period during which operation of the same was withheld upon setting aside of the order dated
25.4.03 and/or in the alternative to direct the Corporation to revive the building plan by granting suitable extension. According to him, the petitioner
was resisted from raising construction on the ground that the Corporation intended to use the said premises for constructing a park but such
proposal not having materialized, the petitioner ought not to be penalized for no fault of his. He, accordingly, urged this Court to grant relief(s) as
prayed for.
6. Mr. Ghosh, learned Counsel for the Corporation vehemently opposed the petition. He referred to Section 398(3) of the Kolkata Municipal
Corporation Act, 1980 (hereafter the Act) and submitted that the petitioner not having commenced construction at the said premises in terms of
the building permit within two years of such sanction, it stood lapsed. Alternatively it is his further submission that since the petitioner did not apply
for revalidation and/or extension of the permit prior to its expiry on 27.10.04, question of grant of revalidation/extension of the same does not and
cannot arise and the petitioner has to apply for fresh sanction if he intends to raise construction. According to him, the petitioner is not entitled to
any relief whatsoever.
7. In reply, Mr. Ali submitted that even if one does not commence construction within two years from date of sanction, the plan does not lapse
automatically as contended by Mr. Ghosh. According to him, the plan subsists till the period of its validity and requirement of the statute is that if
anyone intends to raise construction after two years of sanction he must inform the Corporation intending to commence construction and the
provisions of Section 398 would have application in such a case. It is his further submission that question of the plan lapsing on expiry of five years
from the date of its sanction as contended by Mr. Ghosh, is absolutely misconceived inasmuch as the letter dated 25.4.03 withholding the
operation of the plan is yet to be recalled and, therefore, it cannot be said that the plan has lapsed by operation of law.
8. This Court has considered the rival submissions at the bar. Before this Court proceeds to decide the issues raised herein, a close look at the
statutory provisions, to the extent relevant herein, would be profitable.
9. Chapter XXII of the Act embodies provisions relating to ""Buildings"". Section 392, inter alia, prohibits erection of a building without sanction of
the Municipal Commissioner. In terms of Section 393, a person who intends to erect a building is obliged to apply for sanction to the Municipal
Commissioner by giving a notice in writing of his intention and containing relevant information in a prescribed form. The notice is to be
accompanied by such documents and plans as may be prescribed. Section 395 requires the person intending to build to specify the purpose for
which the building is to be used. Section 396 of the Act provides for sanction or provisional sanction to be granted by the Municipal Commissioner
or his refusal to sanction erection of a building. Cancellation of sanction is permitted under certain conditions in terms of Section 397. Section 398,
inter alia, permits erection of a building after sanction has been given by the Municipal Commissioner as well as steps to be taken by the person
intending to build in the event sanction is not refused by the Municipal Commissioner within the specified time. It also obliges a person, who has not
commenced erection of the building within two years of the sanction, to give a notice u/s 393 for fresh sanction and provides for applicability of the
provisions of this section in relation to such notice as they applied in relation to the original notice. Lastly, the provision requires the person
intending to build to give a notice of proposed date of commencement of erection and that if commencement does not take place within 15 days of
the notified date, to give a fresh notice in this behalf. Section 399 empowers the Municipal Commissioner (when sanctioning the erection of a
building) to specify a reasonable period within which erection thereof is to be completed, and that if erection is not completed within the period
specified, erection shall not be continued except without a fresh sanction or within such extended period as may be allowed by him.
10. Chapter III of the Building Rules, 1990 (hereafter the rules) framed under the Act lays down procedure for sanction for erection of a building.
It obliges a person intending to build to issue notice in writing to the Municipal Commissioner in the form as specified in Schedule I thereto. This
notice is to be accompanied by other documents required under the rules, viz. key plan, site plan, building plan etc. Power of the Municipal
Commissioner to issue sanction or provisional sanction or to refuse sanction is contained in Rule 13. In the event the Municipal Commissioner
sanctions or decides to provisionally sanction the erection of a building, he shall issue a building permit in the form as specified in Schedule VI and
in case of refusal, communication has to be issued in the form as specified in Schedule VII. Rule 15 provides that a building permit, subject to
provisions of Section 398(3), shall be valid for a minimum period of 5 years from date of issue thereof. Rule 21 lays down that proposed date of
commencement of erection has to be notified in the form as specified in Schedule IX within two years from date of issue of the building permit but
not less than seven days before commencement. However, in terms of the proviso thereto, if during the validity of the building permit erection does
not commence within fifteen days of the notified date, the notice shall be deemed not to have been given and a fresh notice shall be necessary if the
validity of the building permit has not expired.
11. It would therefore appear that the aforesaid statutory provisions are regulatory in nature for the purpose of controlled erection of buildings in
the city of Kolkata and, therefore, a construction of the relevant statutory provisions has to be made in such manner so as to give effect to the
legislative intent.
It is not in dispute that building permit was sanctioned in favour of the petitioner by the Municipal Commissioner on 28.11.1999 and was valid till
27.10.2004. However, there is nothing on record to establish that within two weeks from date of issuance of the building permit, the petitioner had
notified his intention of commencing erection in terms thereof as is required by Section 398(4) of the Act. From the petitioner''s own showing, he
intended to commence construction on 20.3.2003, i.e. well beyond two years from date of sanction of the building permit.
12. True it is that by the letter dated 25.4.2003 the building plan was withheld for the time being and construction work was prohibited thereby.
But the question which arises for a decision on facts and in the circumstances of this case is whether on the failure of the petitioners to commence
construction within 27.10.2001, i.e. two years from date of issuance of the building permit, the building permit lapsed by operation of law as
contended by Mr. Ghosh though the building permit was initially valid for a period of five years from date of issue thereof, i.e. till 27.10.2004. This
question has to be answered keeping in mind the provisions of Section 393/398/399 of the Act read with Rule 15 of the rules.
13. The building permit has not been annexed to the present petition. However, the Corporation in its counter-affidavit has not disputed the
assertion of the petitioner that it was valid till 27.10.2004. Issuance of building permit and its validity is regulated by Section 399 of the Act read
with Rule 15 of the rules. As has been noted above, Section 399 empowers the Municipal Commissioner to specify period within which erection
has to be completed. In terms thereof and in exercise of power conferred by Rule 15(3), the building permit had been issued which was to remain
valid for five years from date thereof, but such validity of the building permit is subject to the provision of Section 398(3) according to the same
provision [Rule 15(3)]. When the language of the statute is clear and admits of no ambiguity, it has to be read literally and the words used by the
legislature have to be given their ordinary, natural and grammatical meaning irrespective of its consequences is the cardinal rule of construction of
statutes. To the mind of this Court, once a building permit is issued for a period of five years and the person favoured with the building permit does
neither commence construction within two years from the date of its issuance nor even notifies his intention to commence erection within two years,
he cannot after lapse of the said period of two years raise any construction on the basis of the building permit because it exhausts itself by passage
of time and in terms of Sub-section (3) of Section 398 of the Act, a fresh sanction has to be applied for from the Municipal Commissioner and
provisions of Section 398 is made applicable in relation to a notice for fresh sanction as it applied in relation to the original notice. What Section
398 further envisages is that only upon a fresh sanction granted by the Municipal Commissioner a person intending to build can commence erection
of the building in accordance therewith and in the process he would be bound not to contravene any of the provisions of the Act or the rules
framed thereunder or any other law in force for the time being. If only the petitioner had notified his intention to commence erection on a particular
date within 27.10.2001, i.e. two years from issuance of the building permit and even if he had not commenced erection on the date notified,
proviso to Rule 21 could have been availed of by him, for, in such case the permit would not have lapsed and would have remained valid till its
expiry as specified under Rule 15(3). Non-issuance of any notice notifying intention to commence erection within two years of issuance of the
building permit proves fatal for the petitioner and the position cannot be retrieved for no law permits him to pray for extension/ revalidation of a
lapsed permit. It is understandably true that having obtained a building permit from the Municipal Commissioner, it would amount to some hardship
for the petitioner to repeat the process of obtaining sanction once again. However, law is well-settled to the effect that result flowing from a
statutory provision is never an evil and Court has no power to ignore that provision to relieve what it considers a distress resulting from its
operation; whether the Court likes the result or not, the statute has to be given effect to (See Martin Burn Ltd. Vs. The Corporation of Calcutta, ).
14. In view there of, the conclusion is inevitable that unless and until a fresh sanction is obtained by the petitioner from the Municipal Commissioner
by repeating the procedure as laid down in the statutory provisions referred to above for the purpose of obtention of sanction and commencement
of erection, he is not legally entitled to reap the fruits of the building permit sanctioned on 28.10.1999. The language of Section 398(3) of the Act is
clear and admits of no ambiguity and on literal construction thereof, the contention of Mr. Ghosh is upheld.
15. The submission of Mr. Ali that the very fact that the Executive Engineer of the Corporation by the notice dated 25.4.2003 had withheld the
building plan establishes that the building permit was valid and did not lapse cannot be of any assistance to the petitioner. Since the petitioner had
not commenced construction within two years, the building permit by operation of law had lapsed and the same could not have been given a fresh
lease of life by an order passed by the Executive Engineer. Any action of a public authority which is palpably contrary to the provisions of law
cannot vest a citizen with an enforceable right. The said order for all intents and purposes is non est and is declared so.
16. However, having regard to the correspondences exchanged between the petitioner and the Government, it appears to be clear that the said
premises is no longer required to be acquired for the purpose of a park and, therefore, this Court holds that it would now be open to the petitioner
to apply for fresh sanction of the Municipal Commissioner by giving notice u/s 393 of the Act for erecting a building on it and if such notice is given,
appropriate action in accordance with law shall follow.
17. The writ petition stands disposed of with the aforesaid observations. However, there shall be no order as to costs.