🖨️ Print / Download PDF

Oriental Engineering and Construction Company Vs State of West Bengal

Case No: Award No. 63 of 1970

Date of Decision: Aug. 26, 1970

Acts Referred: Arbitration Act, 1940 — Section 2, 4, 8, 9

Citation: (1974) 1 ILR (Cal) 251

Hon'ble Judges: Masud, J

Bench: Single Bench

Advocate: Sankar Ghose, for the Appellant; Protiva Banerjee, for the Respondent

Final Decision: Dismissed

Translate: English | हिन्दी | தமிழ் | తెలుగు | ಕನ್ನಡ | मराठी

Judgement

Masud, J.@mdashThe Petitioner, Oriental Engineering & Construction Co., has made this application u/s 8 of the Indian Arbitration Act, 1940,

for appointment of N.S. Tayebji, retired Chief Engineer, Indian Railways, or any other person as Arbitrator in respect of the disputes between the

parties. The tender of the Petitioner, as subsequently modified, was duly accepted by the State of West Bengal through the office of the

Superintending Engineer, Western Circle, on November 18, 1966. A formal deed of contract, being B.F. No. 2911 (ii) was executed and the

Petitioner .undertook the works as contemplated by the said tender. After completion of the work the Petitioner submitted a final bill for a sum of

Rs. 3,15,723-94. The State of West Bengal raised various objections to different items in the said final bill. In the premises, disputes and

differences arose between the parties and the Petitioner by the letter dated March 24, 1970, called upon the State of West Bengal to refer the

disputes to arbitration under cl. 25 of the conditions of contract within a fortnight from the date of the receipt of the said letter. The letter was

addressed to the Superintending Engineer, Western Circle, Public Health, Engineering Directorate, and two copies were sent to the Chief

Engineer, Public Health, Engineering Directorate, Government of West Bengal, and also to the Executive Engineer, Calcutta Division, Public

Health, Engineering Department, for information. By a letter dated April 7, 1970, the Superintending Engineer, Western Circle, wrote to the Chief

Engineer, Public Health, Engineering Department, referring the disputes between the parties to the sole arbitration to him under the said arbitration

clause. On May 16, 1.970, Oriental Engineering & Construction Co. wrote to the Superintending Engineer, Western Circle, that as the Chief

Engineer did not enter or proceed with the reference within one month after the request was made by him the Petitioner appointed Sri N. S.

Tayebji to be the sole Arbitrator for settlement of the disputes.- On June 11, 1970, the present application has been filed.

2. Mr. Sankar Ghosh, on behalf of the Petitioner, has drawn my attention to the Explanation to Section 9 of the Arbitration Act and has submitted

that as the Chief Engineer failed to enter on the reference or to appoint his nominee within 30 days from the date when request was made to him to

enter on the reference as set out in the letter of the Respondent dated April 7, 1970, the Petitioner has lawfully appointed N. S. Tayebji as the sole

Arbitrator as communicated to the Respondent by their letter dated May .16, 1970.

3. Mrs. Banerjee, on behalf of the State of West Bengal, has contended that this application is not maintainable u/s 8 of the Act inasmuch as the

Petitioner is bound by the arbitration clause u/s 4 and until the provisions of the said clause are complied with, Section 8 of the Act is not attracted.

4. The application could be disposed of on the short point that as the Chief Engineer has not nominated any person as the Arbitrator under the

arbitration clause the question of removal of the Chief Engineer or his nominee and appointment of Sri Tayebji or any other person as the sole

Arbitrator does not arise. But elaborate arguments have been made by the counsel for both the parties on the scope of Sections 4 and 8. Before

the points of law are discussed, it is necessary to set out the arbitration clause which reads as follows:

Clause 25--Except as otherwise provided in the- contract, all questions and disputes relating to. the meaning of the specifications, designs,

drawings and instructions hereinbefore mentioned and as to the quality of workmanship or materials used on the work or as to any other question,

claim, right, matter or thing whatsoever, in any way arising out of or relating to the contract, designs, drawings, specifications, estimates,

instructions, orders or those conditions or otherwise concerning the works of the execution or failure to execute the same whether arising during the

progress of the work or after the completion or abandonment the $e of, shall be referred to the sole arbitration of the Chief - Engineer of the

department. Should the'' Chief Engineer be for any reason unwilling or unable to act as such Arbitrator, such questions and disputes shall be

referred, to an Arbitrator to be appointed by the Chief Engineer. The award of the Arbitrator shall be final, conclusive and binding on all parties to

this contract.

It is clear from the said clause that the parties have decided their disputes to be determined by reference to arbitration. Further, the parties have

also agreed that the Chief Engineer of the Public Health, Engineering Department would be the sole Arbitrator of the disputes between the parties.

It is further provided that, if the Chief Engineer for any reason is unable or unwilling to act as Arbitrator, the disputes shall be referred to an

Arbitrator to be appointed by the Chief Engineer. Section 4 of the Arbitration Act reads as follows:

The parties to an arbitration agreement may agree that any reference thereunder shall be to an Arbitrator or Arbitrators to be appointed by a

person designated in the agreement either by name or as the holder for the time being of any office or appointment.

Under Section 2 of the Act an arbitration agreement may or may not mention the name of an Arbitrator. But, it is quite possible that the arbitration

agreement instead of mentioning. the name of a person may state the holder of an office to be the Arbitrator. Section 4 of the Act contemplates

cases where the parties have agreed to have their disputes decided by an Arbitrator or Arbitrators to be appointed by a named person or by the

holder of any office. Thus Section 4 deals with those cases where an Arbitrator"" or Arbitrators are to be appointed by a third party. The present

arbitration clause may be construed partly as an arbitration agreement within the meaning of Section 4 of the Act. Section 4 applies to this clause

insofar as the parties agreed that in certain contingencies the Chief Engineer a third party may appoint his nominee as the Arbitrator. But, in the

arbitration clause here it is provided that before an appointment by the Chief Engineer is made the disputes of the parties should be referred to the

arbitration of the Chief Engineer first. This part of the agreement is not covered u/s 4 of the Act. In the premises, the Chief Engineer is the

Arbitrator appointed by the parties and, therefore, he is the appointed Arbitrator within the meaning of Section 8(l)(b) of the Arbitration Act. Mr.

Ghosh has, therefore, argued that the Chief Engineer has neglected or refused to act or is incapable of acting within the meaning of Section 8(l)(b)

and, as such, the Petitioner is justified in serving the notice on the Respondent asking the latter to concur in the appointment of the said Mr.

Tayebji. In my view, Mrs. Banerjee''s contention that the present application is not maintainable u/s 8 read with Section 4 cannot, therefore, be

accepted. Where the arbitration clause contemplates the appointment of an Arbitrator by the parties and also the appointment of an Arbitrator by

third party, Section 4 cannot debar a party from making an application u/s 8(l)(b) if, of course, the other conditions of the said section arc satisfied.

In the facts of, the present case, the Superintending Engineer, Western Circle, informed the agreed Arbitrator, that is, the Chief Engineer, Public

Health, Engineering Department, by letter dated April 7, 1970, requesting him to act as the sole Arbitrator under the arbitration agreement. The

Chief Engineer under the agreement should have replied to the said letter stating his willingness or unwillingness or consent or inability to act as such

Arbitrator. In the present case, the Chief Engineer has not replied to the said letter. It is not alleged that the Chief Engineer did not receive the letter

of the Superintending Engineer, Western Circle. Under the arbitration clause, the Chief Engineer had the option of not consenting to act as the

Arbitrator. But his failure to decide, whether he would be in a position to act as the Arbitrator or not can certainly be construed as neglect or

refusal within the meaning of Section 8(l)(b) of the Act. I am unable to accept the contention of Mrs. Banerjee that until the Chief Engineer accepts

in writing his appointment as the sole Arbitrator he cannot be said to have failed or to have neglected to act within the meaning of the said Sub-

section. If such contention is accepted the appointed Arbitrator by his silence would cause unreasonable delay in the determination of the disputes

between the parties. In the present case, by not replying to the letter appointing him as the sole Arbitrator, the Chief Engineer has impliedly by his

conduct refused to proceed with the reference. The explanation to Section 9 reads as follows:

Explanation: The fact that an Arbitrator or Umpire, after a request by either party to enter on and proceed with the reference, docs not within one

month comply with the request may constitute a neglect or refusal to act within the meaning of Section 8 and this section.

5. Here the Chief Engineer was appointed the Arbitrator on or about April 7, 1970. The Petitioner waited till May 16, 1970, when the Petitioner

served a notice on the Respondent to concur in the appointment of S. N. Tayebji. I, therefore, agree with Mr. Ghosh that this Court has

jurisdiction to entertain this application and it cannot be dismissed for want of jurisdiction. But both Section 8(1) and the explanation to Section 9

have used the word ''may'' in the matter of appointment of an Arbitrator by the Court and, as such, there is an element of exercise of discretion in

such appointment. It is well-settled that the discretion should be exercised judicially. In the present case, the discretion cannot be exercised in

favour of the Petitioner on the following grounds:

Firstly, the appointment of Tayebji would only arise after a proper notice is served on the Respondent. If the arbitration clause would not have

mentioned the appointment of an Arbitrator by the Chief Engineer the notice by the Petitioner dated May 16, 1970, could not be said to be

irregular. But the arbitration clause also has provided that if the Chief Engineer is unwilling or unable to act as Arbitrator, he will have the right to

appoint an Arbitrator to decide the disputes between the parties. It is true that the Chief Engineer has not exercised this power to appoint his

nominee as Arbitrator until to-day. But, even then, the Petitioner should have written to the Respondent or the Chief Engineer that the latter should

either express his decision to act as the Arbitrator himself or to nominate an Arbitrator as set out in the arbitration clause itself. In the present case,

without giving such notice the Petitioner straightway appointed Tayebji as the sole Arbitrator. Under the arbitration clause the Petitioner is bound

by the arbitration not only of the Chief Engineer but also by his nominee. If the Petitioner could have satisfied the Court that the Chief Engineer has

not only failed and neglected to act as the Arbitrator but has also refused to nominate the Arbitrator, the Court might have decided in a different

way. On the contrary, it appears from para. 8 of the affidavit filed on behalf of the Respondent that the Chief Engineer could not enter into the

reference due to heavy pressure of work. It is also stated in the said paragraph that the Chief Engineer approached Sri S. Chatterjee, the Chief

Engineer, C.M.P.O. and Sri B. Bhattacharya, Chief Engineer, Construction Board, to ascertain their views whether any of them would be able to

act as the sole Arbitrator in this matter. In fact, it is stated that both of them expressed their willingness to act as the sole Arbitrator. Thus, it is

obvious that the Chief Engineer not only expressed his inability to act as the Arbitrator but also has taken steps in appointing his nominee. This is

not a case where the appointed Arbitrator or the appointing authority has refused to act as the Arbitrator himself or to nominate an Arbitrator in

terms of the arbitration clause in spite of repeated requests.

Secondly, Section 8(l)(b) has no application in the present case inasmuch as the Arbitrator, in fact, has not yet been appointed and, therefore,

there is no question of neglect or refusal to act by an ''appointed Arbitrator'' within the meaning of Section 8(l)(b). The Chief Engineer is certainly

the appointed Arbitrator; but the Chief Engineer under the arbitration agreement has been given power to appoint an Arbitrator if the Chief

Engineer is unable or unwilling to be the Arbitrator. The distinguishing feature in the present case is that no appointment has been made by the

Chief Engineer and thus the person to be appointed by the Chief Engineer as the Arbitrator cannot be made guilty of neglect or. refusal to act..

Default, if at all, has arisen on the failure of the Chief Engineer as the appointed Arbitrator to enter on or to proceed with the reference. But the

Chief Engineer, as the appointing authority, has not been asked by the Petitioner to nominate a person as the Arbitrator and, as such; the question

of neglect or refusal of the appointing authority or his nominee docs not arise.

6. Relying upon Surendranath Paul Vs. Union of India (UOI), and my own judgment in East India Construction Co. (P) Ltd. Vs. Union of India

(UOI), Mr. Ghosh has argued that the appointment of the Chief Engineer or his nominee as the Arbitrator has been agreed upon by the parties in

the arbitration clause and, as such, the Chief Engineer'' or his nominee is the appointed Arbitrator within the meaning of Section 8(l)(b). The Chief

Engineer has neglected to enter on and proceed with the reference within one month after the request was made to him and, therefore, the Chief

Engineer''s conduct amounts to a neglect or refusal to act within the meaning of Section 8. It is true that the Chief Engineer has failed to act within

one month from the request made to him. It is also true that the Chief Engineer by not nominating or appointing an Arbitrator of his own choice is

virtually not allowing the. reference to proceed. But, in my view, the Chief Engineer''s failure to appoint an Arbitrator within one month after the

request was made to him to act as the Arbitrator cannot be construed as the failure of the appointed Arbitrator to proceed with the reference.

Request was made by the Petitioner to the Chief Engineer for acting as the Arbitrator. As stated above, no request to him had been ""made by the

Petitioner to nominate or appoint an Arbitrator. If after such nomination or appointment of an Arbitrator by the Chief. Engineer, the said nominated

or appointed Arbitrator does not enter on or proceed with the reference such act on the part of such nominee would amount to a neglect or refusal

within the meaning of Section 8(l)(b). In any event, the period, of one month mentioned in Explanation to Section 9 cannot be construed as a

period of limitation on the expiry of which, the remedy of the Respondent is barred. Mrs. Banerjee has relied upon Union of India v. New India

Constructors, Delhi, and Ors. in this connection. It should be remembered that in all these three cases the agreed Arbitrator or the appointing

authority has exercised their option to appoint an. Arbitrator and, as such, there has been an ''appointed Arbitrator'' Within the meaning of Section

8(l)(b). Both in Surendra Nath Paul v. Union of India (Supra ) and Union of India (UOI) Vs. New India Constructors, Delhi and Others, the

question was whether the power of the named Arbitrator to appoint another Arbitrator is exhausted after he has exercised his power once to

nominate an Arbitrator. "" Mr. Ghosh has argued that those two decisions support his contention that the appointment by the Chief Engineer is the

result of consent of the parties themselves and, as such, the nominee of the Chief Engineer is also an ''appointed Arbitrator. As stated earlier, there

is no doubt that the parties have consented to the appointment of the Chief Engineer and also to the appointment of an Arbitrator by the Chief

Engineer. The power to appoint Arbitrator by the Chief Engineer or the machinery or procedure to appoint an Arbitrator in the event of the . Chief

Engineer''s inability or unwillingness to act as the Arbitrator has certainly been the result of the consent of the parties. But, in order to attract

Section 8(l)(b) the Petitioner must satisfy the Court that the appointed Arbitrator, ''in this case, the Chief Engineer, has failed or neglected or

expressed his -inability to act, which term includes his inability to nominate. In the Division Bench case, the Secretary, Ministry of Works, Housing

and Supplies, and in the. second case, the General Manager as the third party or the appointed Arbitrator did, in fact, exercise their power to

appoint an Arbitrator and, as such, there has been art appointed Arbitrator within the meaning of Section 8(l)(b).

7. Mrs. Banerjee has relied upon Union of India v. New India Constructors, Delhi and Ors. (Supra ) in support of her contention that in the

present case the Chief Engineer has not failed or neglected to act inasmuch as the Chief Engineer has not expressed his unwillingness to act as the

Arbitrator. According to her, the failure to act would only arise when the Chief Engineer has accepted his appointment as the Arbitrator.

Admittedly in the present case, although the Chief Engineer was requested by the Petitioner to act as the Arbitrator on April 7, 1970, the Petitioner

waited for more than a month for getting an intimation from him and on May 16, 1970, suggested the name of Mr. Tayebji as the Arbitrator for the

consent of the Respondent. It is not denied that the Chief Engineer received the said letter in due course and it must be construed that the Chief

Engineer by his conduct has expressed his unwillingness to act as the Arbitrator. I am not willing to accept the contention that unless and until the

Chief Engineer expresses his inability or unwillingness to act in writing, he cannot be blamed for neglect, refusal or inability to act as the Arbitrator.

It may be added here that in the Punjab case although the learned Judges have indicated that Section 8(l)(b) has no application in the facts of that

case and yet, in fact, they did appoint an Arbitrator.

8. Lastly, it has been argued by Mr. Ghosh that this application is also maintainable u/s 8(l)(a). Relying upon Surendra Nath. Pant v. Union of India

(Supra ) and East India Construction Co. Pvl. Lid. v. Union of India (Supra ) he has reiterated his argument that in the present case the Chief

Engineer or his nominee has been appointed by consent. of the parties, and as there is no, concurrence in such appointment and as the arbitration

proceedings could not commence on account of want of concurrence in the appointment the Court, should appoint an Arbitrator. u/s 8(l)(a) an

Arbitrator is to be appointed by consent of the parties. If, however, such appointment by consent is not possible any party may serve the other

party with a written notice to concur in the appointment of a person of his choice as the proposed Arbitrator. As stated earlier, the machinery or

the procedure to appoint an Arbitrator has been agreed upon by the parties. But, there must be a proposal of a particular person from one side in

whose appointment the other party has not concurred. In the instant case, the Chief Engineer has not appointed or proposed a person as the

Arbitrator. Therefore, no situation has arisen where the Petitioner has not concurred in the appointment of an Arbitrator. Section 8(l)(a) arises only

when an Arbitrator or Arbitrators are to be appointed by consent of the parties; it cannot contemplate cases where a particular person or his

nominee is agreed to be the Arbitrator and there is no option for one party or the other to suggest or to agree to an Arbitrator. Reference may be

made to my observation on this point in East India Construction Co, Pvt. Ltd. v. Union of India (Supra). It should be remembered that the

question of neglect or refusal to act as the Arbitrator is not contemplated. in Section 8(l)(a) of the Act The Petitioner''s case is that the Chief

Engineer has failed or neglected to take steps in the commencement of the reference and not that the person to be appointed by the parties has not

been agreed upon by the Petitioner.

9. For all the reasons stated above this application must be dismissed. But there will be no order as to costs. It may be stated, however, that the

Respondent has expressed in para. 8 of the affidavit affirmed by Satyabrata Kundu on behalf of the Respondent that the Chief Engineer already

approached two persons to'' ascertain their views if they would be willing to act as the sole Arbitrator in this matter. Be that as it may, the Chief

Engineer is directed to appoint an Arbitrator in accordance with the arbitration agreement within three weeks from to-day so that disputes between

the parties may be determined without further delay.