🖨️ Print / Download PDF

Arun Construction Co. Vs The Bombay Housing and Area Development Board and another

Case No: Suit No.1313 of 1981 with Suit No. 1315 of 1981

Date of Decision: Dec. 4, 1999

Acts Referred: Bombay Port Trust Act, 1879 — Section 87#Civil Procedure Code, 1908 (CPC) — Section 9#Contract Act, 1872 — Section 73#Limitation Act, 1963 — Section 3#Maharashtra Housing and Area Development Act, 1976 — Section 173

Citation: (2000) 1 ALLMR 3 : (2000) 2 BomCR 450 : (2000) 1 BOMLR 509 : (2000) 2 MhLj 239

Hon'ble Judges: D.K. Deshmukh, J

Bench: Single Bench

Advocate: Nitin Vhatkar instructed by T.N. Tripathi, for the Appellant; Behram Shroff, for the Respondent

Translate: English | हिन्दी | தமிழ் | తెలుగు | ಕನ್ನಡ | मराठी

Judgement

@JUDGMENTTAG-ORDER

D.K. Deshmukh, J.@mdashBoth the suits are filed by the same plaintiffs, defendants are also common, the question that arises for decision is also

the same. Therefore, both the suits can be conveniently disposed of by a common order.

2. In both the suits, issue of limitation has been framed i.e. Issue No. 7 which reads as under :-

Whether the suit filed by the plaintiffs is within limitation?

Both the parties have agreed to try this issue as preliminary issue. The learned Counsel for the defendants made a statement that he accepts for the

purpose of decision of this issue, averments in paragraph 16 of the plaint in both the suits. Both the suits have been filed by the plaintiffs for a

decree of damages against the defendant No. 1. According to the plaintiffs, tenders were Invited by the defendants for some work to be carried

out. The plaintiffs submitted the tender. According to the plaintiffs, tender of the plaintiffs was accepted. However, the work was not commenced.

According to the plaintiffs, as a result of acceptance of the tender, a binding contract between the parties has come into existence. According to

the plaintiffs, - the defendants have committed breach of that contract and therefore, these suits have been filed for damages suffered by the

plaintiffs for the breach of the contract committed by the defendants. The averments in paragraph 16 of these suits are relevant for deciding the

issue of limitation. Paragraph 16 of Suit No. 1313 of 1981 reads as under :-

16. That the defendants created their liability by issue of letters dated 19th July 1978 and 14th September 1978, which are the root cause for the

cause of action of the subject matter of the present suit. The plaintiffs are filing the suit for the damages and or compensation or loss of profit within

three years from the date when the cause of action arose. The plaintiffs'' suit is therefore not barred by the law of limitation.

Paragraph 16 of Suit No. 1315 of 1981 reads as under :-

16. That the defendants created their liability by issue of letters dated 19th July 1978 and 14th September 1978, which are the root cause for the

cause of action of the subject matter of the present suit. The plaintiffs are filing the suit for the damages and or compensation or loss of profits

within three years from the date when the cause of action arose. The plaintiffs'' suit is therefore not barred by the laws of limitation.

3. Both the suits have been filed on the same day in this Court i.e. 10th July 1981. Perusal of paragraph 16 of both the suits quoted above shows

that according to the plaintiffs themselves, the cause of action for filing of these suits arose in the month of July 1978. The suits have been filed in

July 1981. The learned Counsel for the defendants relies on the provision of section 173 of Maharashtra Housing and Area Development Act,

1976. He submits that the limitation that is provided by this section for filing of the suit claiming damages against the authority constituted under the

Act is six months from the date of accrual of the cause of action. In support of this submission, he relied on the judgment of the Supreme Court in

the case of The Trustees of Port of Bombay Vs. The Premier Automobiles Ltd. and Another, .

4. The learned Counsel appearing for the plaintiffs submits that the period of six months mentioned in section 173 is a period for issuing notice of

two months. In the submission of the learned Counsel. Section 173 does not lay down any period of limitation for institution of a suit. In the

submission of the learned Counsel, a suit cannot be instituted against the authority under the Act without giving that authority a notice of two

months and that notice has to be issued within a period of six months from the date of the accrual of the cause of action.

5. Now, if in the light of these rival submissions section 173 is perused, to my mind, it is clear that once section 173 lays down two requirements

for valid institution of a suit against the authority viz(1) service of two months'' notice on the authority and (2) institution of the suit within six months

from the accrual of the cause of action. Perusal of the judgment of the Supreme Court in the case of the Trustees of Port of Bombay referred to

above shows that in that case the Supreme Court was construing the provisions of section 87 of the Bombay Port Trust Act. Section 87 of the

Bombay Port Trust Act, which is quoted in paragraph 8 of the judgment of the Supreme Court reads as under :-

87. No suit or other proceeding shall be commenced against any person for any thing done, or purporting to have been done, in pursuance of this

Act, without giving to such person one month''s previous notice in writing of the intended suit or other proceeding and of the cause thereof, nor

after six months from the accrual of the cause of such suit or other proceeding .............

A comparison of provisions of section 87 of the Bombay Port Trust Act and section 173 of the Act shows that the provisions are of para materia.

Perusal of the judgment of the Supreme Court has considered the provisions of section 87 in detail and has held that section 87 deals with

limitation for institution of a suit. To my mind, it is clear that section 173 does not deal with merely with the period within which notice is to be

given, but it clearly lays down the period of limitation for institution of a suit. Placing any other interpretation on the provisions of section 173 would

amount to doing violence to the language in which the section is couched. It is thus clear that when the section lays down the period of six months it

is referring to the commencing of the suit and not to the giving of the notice. It is clear that the said section in clear terms lays down that two months

previous notice has to be given to the authority who would be a party of the intended suit and the cause thereof and the suit has to be instituted

within six months of the cause of action. In the present case, it is clear that both the suits have not been instituted within a period of six months from

the date on which according to the plaintiffs themselves, the cause of action arises. It has therefore to be held that both the suits have not been

instituted within a period of six months as contemplated by provisions of section 173 and therefore, both the suits are barred by limitation. Issue

No. 7 in both the suits is therefore answered accordingly. In view of the finding recorded on issue of limitation, the suits do not survive and the

same are dismissed with costs.

Certified copy expedited

6. Suits dismissed.